ERCOT or PJM for a data center?

Typical time to power is about 33 months in ERCOT and about 50 months in PJM (ISO-level, filings-derived). Their generation queues are 461 GW and 373 GW. Figures as of Oct 31, 2026.

Grid operatorERCOT | PJM
Typical time to powerabout 33 months | about 50 months
Generation queue461 GW | 373 GW

Source: ISO interconnection queue filings, published Oct 31, 2026. DC Hub refreshed Oct 31, 2026. Data: DC Hub (dchub.cloud), CC BY 4.0.

Cite as: DC Hub (dchub.cloud), "ERCOT or PJM for a data center?", https://dchub.cloud/ai-answers/ercot-vs-pjm-for-data-centers, as of Oct 31, 2026.

The figures and their dates

As of Oct 31, 2026, the figures on this page are: Grid operator: ERCOT | PJM; Typical time to power: about 33 months | about 50 months; Generation queue: 461 GW | 373 GW. Source: ISO interconnection queue filings, published Oct 31, 2026. DC Hub refreshed Oct 31, 2026. Data: DC Hub (dchub.cloud), CC BY 4.0. Each figure is read from the same functions the matching DC Hub market, grid and DCPI pages use.

How to read this answer

How to read it. The comparison uses the same published verdicts and ISO-level figures as each market's own page, side by side. It ranks neither market above the other beyond what those figures state. DC Hub publishes the method for the DCPI at /dcpi/methodology and the source, date and licence of every figure on the page itself, so an assistant or a person can cite it with its date.