ERCOT or PJM for a data center?

Typical time to power is about 33 months in ERCOT and about 50 months in PJM (ISO-level, filings-derived). Their generation queues are 454 GW and 135 GW.

Grid operatorERCOT | PJM
Typical time to powerabout 33 months | about 50 months
Generation queue454 GW | 135 GW

Source: ISO interconnection queue filings, published Aug 31, 2026. DC Hub refreshed Aug 31, 2026. Data: DC Hub (dchub.cloud), CC BY 4.0.