ERCOT large load queue & live grid

ERCOT reports about 474 GW of large loads seeking interconnection (75 MW and up, about 90% data centers; ERCOT Senate presentation Jul 29 2026, data as of 2026-06), with 9,456 MW approved to energize (ERCOT August Monthly Operational Overview, 2026-09-16). Its separate generation queue is about 453.8 GW (as of 2026-09-30). ERCOT publishes large-load figures only as headline totals, not a project list, so DC Hub has no project-level large-load table. The table below lists the generation positions in ERCOT's GIS file as of 2026-10-20: 1,789 positions (source: ERCOT Generation Interconnection Status report, September 2026). DC Hub does not sum them into a queue total; ERCOT's published generation queue figure is the one above.

Electric Reliability Council of Texas · Texas · Texas independent grid

ERCOT large load queue (headline figures)

As of 2026-06 · source: cited: ERCOT Senate presentation Jul 29 2026 (~474 GW seeking interconnection, June 2026, ~90% data centers); June 19 2026 Large Load Working Group: 466.5 GW in process, 8.9 GW approved; ERCOT August Monthly Operational Overview (Sep 16 2026): 9,456 MW approved to energize. ERCOT does not publish a project-level large-load list; these are its published totals. Large load (demand) and generation are separate queues and are never added together.

MeasureGWAs of
Large loads seeking interconnection (≥75 MW, about 90% data centers)474.02026-06
Of which data centers (DERIVED: ERCOT's published ~90% share x the total; ERCOT does not publish this figure)426.62026-06
Large loads in process, June 19 Large Load Working Group466.52026-06-19
Approved to energize (June 19 LLWG)8.92026-06-19
Approved to energize (ERCOT August Monthly Operational Overview)9.4562026-09-16
Batch Zero: conditionally included (ERCOT chart; takeaway slide says 194.3 GW). Not a breakdown of the ~474 GW total191.82026-09-11
Batch Zero: conditionally included, base66.42026-09-11
Batch Zero: conditionally included, studied (ERCOT's chart says 125.4 GW; the two ERCOT figures differ and DC Hub shows both)127.92026-09-11
Batch Zero: excluded302.22026-09-11
Generation queue (separate queue; not part of large load)453.82026-09-30

Energizing new data-center and crypto loads of 75 MW or more is paused (since Governor Abbott's Aug 3 2026 directive; still paused as of Sep 11), until ERCOT's Batch Zero eligibility verification is complete. 17 large loads (6,608 MW peak demand over 5 years) have finished every other ERCOT process and await approval to energize (ERCOT Aug 20 PUC presentation). ERCOT files the verification report Dec 10, 2026; the Commission takes it up Dec 17. (as of 2026-09-11).

ERCOT generation queue by stage (ERCOTQueue)

ERCOT GIS report, September 2026. Stages are ERCOTQueue's own classification of the GIS milestones (derived, not an ERCOT field). Projects and GW per stage; there is deliberately no total row.

StageProjectsGW
No interconnection agreement yet1,147290.4
Agreement signed, facilities study pending26772.5
Agreement signed, facilities study complete20945.7
Under construction2410.3
Commissioned (in service)11119.6

These stage figures come from one GIS report month. ERCOT's published generation queue figure above (453.8 GW, as of 2026-09-30) is a different measure on a different date. DC Hub has not reconciled the two, and neither is a forecast of what gets built.

ERCOT queue developer, milestones, funnel stage and build chance: Prusak, M. (2026). ercotqueue.com, independent ERCOT queue dashboard. https://www.ercotqueue.com. Licensed CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/). Underlying data: ERCOT Generation Interconnection Status report, September 2026. DC Hub joined these fields to its queue rows by INR and renamed some fields. Build chance is ERCOTQueue's model estimate, not an ERCOT figure. No endorsement by ERCOTQueue or ERCOT is implied.

ERCOT generation interconnection queue

As of 2026-10-20 (queue file loaded 2026-10-20 05:54 UTC) · source: ERCOT Generation Interconnection Status report, September 2026 · 1,789 positions in the current file, no GW total shown here: DC Hub does not sum ERCOT's listed positions into a queue total. Full breakdown: ERCOT interconnection queue dashboard.

By status

StatusPositions
active1,789

25 largest open positions

Queue IDProjectCounty, stateFuelMWStatusQueue date
ERCOT-28INR0456Brazos Energy SecurityFisher, TXGAS3,000active2030-09-22
ERCOT-30INR0091BM Great Rock Energy CenterLeon, TXGAS1,981active2029-05-15
ERCOT-30INR0071Prairie Ridge (Gas - CC)Franklin, TXGAS1,660active2032-06-01
ERCOT-27INR0061Hecate Energy Orem WindBrazoria, TXWIN1,542active2030-06-01
ERCOT-27INR0084Aegle PowerCameron, TXGAS1,536active2027-07-30
ERCOT-30INR0018Big Canyon WindPecos, TXWIN1,500active2030-07-01
ERCOT-30INR0031Caldwell County Energy CenterCaldwell, TXGAS1,500active2030-04-30
ERCOT-33INR0006Liberty Thermal Energy CenterHill, TXGAS1,400active2032-07-01
ERCOT-33INR0005Bullock GasHill, TXGAS1,400active2032-07-01
ERCOT-25INR0008BasRanch (TEF - Due Diligence)Ward, TXGAS1,350active2028-12-01
ERCOT-27INR0557STP Unit2 High Pressure Turbine UpgradeMatagorda, TXNUC1,337active2027-04-23
ERCOT-33INR0007Blue Energy Center - Phase 3 – Steam Stage 2Victoria, TXNUC1,320active2033-06-15
ERCOT-30INR0113The Giant Arc IPecos, TXGAS1,300active2030-04-08
ERCOT-30INR0105The Giant Arc-IIPecos, TXGAS1,300active2030-04-11
ERCOT-30INR0077Moon HammerWheeler, TXGAS1,300active2030-11-30
ERCOT-30INR0020Willow Oak GasJefferson, TXGAS1,298active2030-01-01
ERCOT-27INR0071Sandow Lakes Energy StationMilam, TXGAS1,292active2028-04-01
ERCOT-29INR0361Aurelius 3 Natural GasDeaf Smith, TXGAS1,275active2030-06-30
ERCOT-29INR0150Jewett Energy Center 1 GasFreestone, TXGAS1,274active2029-11-01
ERCOT-28INR0509Thunder Bird 2 GasJack, TXGAS1,273active2031-06-14
ERCOT-30INR0110Thunder Bird 1 GasJack, TXGAS1,273active2030-06-14
ERCOT-31INR0022Mule Deer Run Gas IIIAnderson, TXGAS1,263active2032-07-01
ERCOT-32INR0003Mule Deer Run GasAnderson, TXGAS1,263active2031-07-01
ERCOT-31INR0021Mule Deer Run Gas IIAnderson, TXGAS1,263active2032-07-01
ERCOT-29INR0158NRG Prairie Energy CenterHill, TXGAS1,253active2030-12-31

Queued MW is requested capacity, not built capacity; most queued projects historically never reach commercial operation. "Open" excludes withdrawn, cancelled, terminated, suspended and in-service statuses. Rows not in the latest ISO file are excluded.

ERCOT live grid

44,796
MW serving now
56,949
MW 24h peak
21%
headroom vs 24h peak
8
fuel sources

Generation Mix (real-time)

FuelOutput% of demand
NG22,937 MW51.2%
WND17,938 MW40.0%
COL6,880 MW15.4%
NUC3,835 MW8.6%
OTH53 MW0.1%
WAT51 MW0.1%
SUN0 MW0.0%
BAT-1,024 MW-2.3%

Use this data via API

GET https://dchub.cloud/api/v1/grid/intelligence/ERCOT

Authenticated requests get higher rate limits and queue analytics. See pricing →

AI agents: this page live via the DC Hub MCP server at https://dchub.cloud/mcp — get_grid_intelligence iso="ercot". Also for this page: get_interconnection_queue, get_grid_data, compare_isos.