Power and grid intelligence across 331 scored markets, refreshed daily. Verdict shifts, BUILD/AVOID watch lists, interconnection-queue depth, and the latest published PJM and ERCOT fuel mix — machine-readable, CC-BY-4.0.
The power market is decisively constrained: 202 of 331 markets (61%) warrant avoidance, while only 26 (8%) qualify as build-ready. SPP emerges as the standout performer with 100% build coverage and an average excess capacity score of 68.9, making it the only ISO delivering consistent greenfield optionality. Within SPP, North Kansas City leads with a 71.6 composite and 12.9-month time-to-power, offering the lowest execution friction in a tight market. ERCOT's Texas footprint, despite iconic renewable penetration at 48.4%, ranks bottom-tier at 5.9% build coverage—Midland–Odessa's exceptional 80.6 score notwithstanding—weighed down by a 31.1-month average TTP and a staggering 51.4-point constraint score. MISO deteriorates further to 2.7% build, crippled by Brandon and Jackson markets posting 24.7 and 24.1 constraint ratings respectively. The verdict skew toward AVOID is structural, not cyclical: 1,459.4 GW sits in the US generation interconnection queue while ERCOT's large-load queue alone carries 474 GW (90% data-center attributed), creating a multi-year supply-demand inversion.
This distribution signals sustained power scarcity through Q1 2027. Queue depth and TTP metrics confirm the squeeze will persist: even SPP's 16.0-month average TTP reflects 2026-era overshooting, while ERCOT and CAISO both clock 31.1 months, effectively locking new capacity behind 2.5-year development cycles. Curtailment pressure, indexed through constraint scores, averages 39.0 in WECC and 52.8 in CAISO—levels incompatible with nine-figure capex confidence. Hyperscalers hunting 2027 power must prioritize SPP's remaining parcels and ERCOT bolt-ons with pre-queue PPA coverage. Otherwise, patience on greenfield remains the prudent position: waiting for gen queue absorption (12–18 months out) will yield materially lower TTP and constraint risk than committing today to markets averaging 24-month build delays.
| Market | ISO | Composite | TTP (mo) |
|---|---|---|---|
| Midland–Odessa | ERCOT | 80.6 | — |
| Williston, ND | MISO | 76.9 | — |
| Cheyenne | WECC | 74.8 | — |
| North Kansas City | SPP | 71.6 | — |
| Gilbert | WECC | 69.8 | — |
| Montréal | HQ | 69.8 | — |
| Tucson | WECC | 69.6 | — |
| Scottsdale | WECC | 69.2 | — |
| Tempe | WECC | 69.0 | — |
| Kansas City | SPP | 68.9 | — |
| Market | ISO | Constraint |
|---|---|---|
| Billings | WECC | — |
| Québec City | HQ | — |
| Brandon | MISO | — |
| Jackson | MISO | — |
| Sheridan | WECC | — |
| Bismarck | MISO | — |
| Sioux Falls | MISO | — |
| Fargo | MISO | — |
| Sioux City | MISO | — |
| Providence | ISONE | — |
| ISO | Markets | BUILD % | Avg Excess | Avg Constraint | Avg TTP (mo) |
|---|---|---|---|---|---|
| AESO | 2 | 0% | — | — | — |
| CAISO | 14 | 14% | — | — | — |
| CEN | 1 | 0% | — | — | — |
| ERCOT | 17 | 6% | — | — | — |
| HQ | 2 | 50% | — | — | — |
| ISONE | 11 | 0% | — | — | — |
| MH | 1 | 0% | — | — | — |
| MISO | 37 | 3% | — | — | — |
| NORDPOOL | 4 | 0% | — | — | — |
| NYISO | 9 | 0% | — | — | — |
| ONS | 2 | 0% | — | — | — |
| PJM | 8 | 0% | — | — | — |