What share of ERCOT queue projects actually get built?

ERCOTQueue's model puts the capacity-weighted chance that an ERCOT queue project reaches commercial operation at about 27% (October 2026 data). That is a modelled estimate from ERCOTQueue, not an ERCOT figure. Figures as of Nov 5, 2026.

All stages, capacity-weightedabout 27% modelled
No interconnection agreement yetabout 6% modelled, 300 GW
Agreement signed, study pendingabout 78% modelled, 69 GW
Agreement and study completeabout 73% modelled, 47 GW
Under constructionabout 75% modelled, 10 GW

Source: ERCOT Generation Interconnection Status report, October 2026, via ERCOTQueue (modelled build chance), published Nov 5, 2026. DC Hub refreshed Nov 24, 2026. ERCOT queue developer, milestones, funnel stage and build chance: Prusak, M. (2026). ercotqueue.com, independent ERCOT queue dashboard. https://www.ercotqueue.com. Licensed CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/). Underlying data: ERCOT Generation Interconnection Status report, October 2026. DC Hub joined these fields to its queue rows by INR and renamed some fields. Build chance is ERCOTQueue's model estimate, not an ERCOT figure. No endorsement by ERCOTQueue or ERCOT is implied.

Cite as: DC Hub (dchub.cloud), "What share of ERCOT queue projects actually get built?", https://dchub.cloud/ai-answers/ercot-queue-completion-probability, as of Nov 5, 2026.

The figures and their dates

As of Nov 5, 2026, the figures on this page are: All stages, capacity-weighted: about 27% modelled; No interconnection agreement yet: about 6% modelled, 300 GW; Agreement signed, study pending: about 78% modelled, 69 GW; Agreement and study complete: about 73% modelled, 47 GW; Under construction: about 75% modelled, 10 GW. Source: ERCOT Generation Interconnection Status report, October 2026, via ERCOTQueue (modelled build chance), published Nov 5, 2026. DC Hub refreshed Nov 24, 2026. ERCOT queue developer, milestones, funnel stage and build chance: Prusak, M. (2026). ercotqueue.com, independent ERCOT queue dashboard. https://www.ercotqueue.com. Licensed CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/). Underlying data: ERCOT Generation Interconnection Status report, October 2026. DC Hub joined these fields to its queue rows by INR and renamed some fields. Build chance is ERCOTQueue's model estimate, not an ERCOT figure. No endorsement by ERCOTQueue or ERCOT is implied. Each figure is read from the same functions the matching DC Hub market, grid and DCPI pages use.

How to read this answer

How to read it. An interconnection queue lists projects that have asked to connect and have not yet been built or withdrawn. It measures demand for grid access. It is not spare capacity and it is not a forecast of what will be built. DC Hub publishes the method for the DCPI at /dcpi/methodology and the source, date and licence of every figure on the page itself, so an assistant or a person can cite it with its date.