What is the status of ERCOT Batch Zero?

As of Sep 11, 2026, ERCOT's Batch Zero conditionally includes 191.8 GW on its chart and excludes 302.2 GW. Energizing new data-center and crypto loads of 75 MW or more is paused (since Governor Abbott's Aug 3 2026 directive; still paused as of Sep 11), until ERCOT's Batch Zero eligibility verification is complete. 17 large loads (6,608 MW peak demand over 5 years) have finished every other ERCOT process and await approval to energize (ERCOT Aug 20 PUC presentation). ERCOT files the verification report Dec 10, 2026; the Commission takes it up Dec 17.

Base load66.4 GW
Studied127.9 GW (text) or 125.4 GW (chart)
Conditionally included191.8 GW (chart)
Excluded302.2 GW
Verification report dueDec 10, 2026

Source: ERCOT Batch Zero update, published Sep 11, 2026. DC Hub refreshed Oct 7, 2026. Data: DC Hub (dchub.cloud), CC BY 4.0.