A live monthly readout of the global data center market: facilities discovered, capacity changed hands, deal volume, AI-agent queries, and per-market trends. Every number is pulled from DC Hub's live ingest pipeline — no spreadsheet versioning, no quarterly lag.
DC Hub's Data Center Power Index (DCPI) scores 334 data-center markets on power availability: 28 BUILD, 104 CAUTION and 202 AVOID. DC Hub tracked 6 data-center deals in August 2024, 6 of them verified ($16.0B verified value). The facility count and total MW are withheld until source records are deduplicated.
Cite as: DC Hub (dchub.cloud), as of 2026-11-26. https://dchub.cloud/reports/monthly/2024-08
August 2024 logged six transactions worth $16 billion and 2,100 MW of capacity—a 268 percent surge in deal value month-over-month and a doubling of transaction count year-over-year. The headline was institutional capital moving decisively into hyperscale infrastructure: Digital Realty and Blackstone closed a $7 billion acquisition on August 8th, while Blue Owl and Chirisa purchased a CoreWeave JV asset for $5 billion on August 1st. Microsoft and AES jointly acquired a renewable-linked data-center platform for $2 billion on August 15th. These three transactions alone accounted for $14 billion of the month's total and signal a structural shift toward energy-secured, build-to-suit models. Regionally, activity remained concentrated in power-constrained and renewables-rich geographies: Richland Parish (5,000 MW across nine facilities), Las Cruces (4,500 MW in a single asset), and Ashburn (4,296 MW across 160 facilities) dominated the inventory landscape.
The velocity and check size of August's M&A flow indicate that capital formation around grid-available capacity will remain the binding constraint through Q4 2024 and into 2025. With 2,100 MW turning over at an average deal price of $7.6 million per megawatt, we expect continued institutional appetite for stabilized, power-secure assets in markets where interconnection queues remain deep and renewable PPAs lock in marginal cost. The 20 percent month-over-month rise in deal count—from five in July to six in August—coupled with a 100 percent year-over-year increase, suggests deal cadence will not abate. Watch for secondary-market consolidation and sponsor-to-sponsor exits as the year closes; dry powder remains substantial, but deployed capital is increasingly selective about fuel type and transmission headroom.
| Date | Buyer | Seller | Value | MW |
|---|---|---|---|---|
| 2024-08-08 | Digital Realty/Blackstone | Hyperscale JV | $7.0B | 1,000 |
| 2024-08-01 | Blue Owl/Chirisa | CoreWeave JV | $5.0B | 500 |
| 2024-08-15 | Microsoft/AES | US Renewable JV | $2.0B | — |
| 2024-08-01 | Meta | Spain Campus | $1.2B | 400 |
| 2024-08-01 | Microsoft | Indonesia Campus | $600M | 150 |
| Market | Facilities | Operating MW |
|---|---|---|
| Richland Parish | 9 | 5,000 |
| Las Cruces | 1 | 4,500 |
| Ashburn | 160 | 4,296 |
| Abilene | 4 | 2,950 |
| Sweetwater | 4 | 2,200 |
| Lebanon | 7 | 2,002 |
| Memphis | 8 | 2,000 |
| Mason County | 1 | 2,000 |
| West Texas | 1 | 2,000 |
| Dallas | 80 | 1,726 |
| Market | DCPI Score | Δ Week |
|---|---|---|
| Power Index movers are on the DC Hub plan with every tool: they are chosen by the size of the 7-day move in the paid excess-power score. | ||
| Market | Projects | Pipeline MW |
|---|---|---|
| CA | 62 | 34,604 |
| Texas | 39 | 28,382 |
| India | 18 | 11,895 |
| Paducah, Kentucky | 4 | 9,600 |
| VA | 12 | 8,834 |
| AZ | 23 | 8,534 |
| New Mexico | 5 | 8,300 |
| Pennsylvania | 4 | 7,775 |
| IL | 11 | 7,743 |
| Ohio | 6 | 7,150 |
Not shown: 246 pipeline projects (170,230 MW) with no market recorded.
These sentences are free for journalists, analysts, and partners to use with attribution to DC Hub. Numbers are live as of 2026-11-26.
"August 2024 saw 6 tracked M&A transactions ($16.0B in aggregate disclosed value), a count that increased 20.0% from the prior month."— DC Hub · https://dchub.cloud/reports/monthly/2024-08
"2,100 MW of capacity changed hands through M&A and JV transactions tracked by DC Hub in August 2024."— DC Hub · https://dchub.cloud/reports/monthly/2024-08
This snapshot is regenerated every time the page is loaded — no quarterly lag, no spreadsheet versioning. Historical months are immutable: /reports/monthly/2026-04 always shows April 2026's numbers as snapshotted when April closed. Same data is also available via:
/api/v1/reports/monthlyhttps://dchub.cloud/mcp (for AI agents)DC Hub. (2026). Monthly Data Center Trend Report. https://dchub.cloud/reports/monthly. Licensed CC-BY-4.0.