📰 Press Release

ERCOT's 427 GW interconnection queue now holds 39% of all US requested load — time-to-power extends into the multi-year range

Queue depth signals capacity planners to price energization delay into any new Texas site decision

PRESS RELEASE June 30, 2026

CORRECTION (2026-10-02): This release said ERCOT's interconnection queue held 427 GW, "39% of all US queued load". The 39% was a ratio of ERCOT's large-load queue to a generation-queue total, not a share of US queued load, and is withdrawn. DC Hub's canonical ERCOT figures: large-load queue 474.0 GW (as of 2026-06, ERCOT-published); data-center portion 426.6 GW (derived: ~90% of the large-load total); generation interconnection queue 461.4 GW (as of 2026-10-31), a separate queue. A load queue and a generation queue must not be divided or added. Current figures: https://dchub.cloud/api/v1/interconnection-queue/snapshot

Highlights

ERCOT's interconnection queue now stands at 427 GW of requested load, accounting for 39% of all queued capacity across US ISOs as of June 30, 2026. That concentration—nearly two-fifths of the nation's pipeline in a single grid—means time-to-power for new large loads in Texas has stretched well beyond 24 months for most substations, and in many cases into the three- to four-year range.

What it means for site selection

If you are evaluating a greenfield or expansion site in ERCOT territory, the queue depth is now a first-order input to your go/no-go model. A substation with 2+ GW already in the study process will not energize a new 100 MW load in 2027—or even 2028—without either a grid upgrade funded by the developer or a willingness to accept curtailment risk during peak intervals. Capex models that assume 18-month commissioning timelines in Texas are obsolete; add 12–24 months of interconnection lag, or look to markets with sub-100 GW queues (SPP, MISO non-metro zones) where study cycles remain under two years.

The second-order risk

The 427 GW figure also implies that generator interconnection and load interconnection are now competing for the same substation capacity in ERCOT's most attractive zones (West Texas wind corridors, metro-adjacent industrial parks). A hyperscaler signing a lease in 2026 may find that the utility's five-year capital plan already allocated the next tranche of transformer capacity to a solar-plus-storage project filed six months earlier. In practice, this means land control and utility pre-coordination must happen in parallel, not sequentially, and that time-to-power is now as much a function of queue position as it is of on-site construction speed.

Source: DC Hub Data Center Power Index (https://dchub.cloud/dcpi). Updated daily. ERCOT interconnection queue data: https://www.ercot.com/misdownload/servlets/mirDownload?doclookupId=1233678977


Press inquiries: press@dchub.cloud · DC Hub MCP API: https://dchub.cloud/mcp