US interconnection queues by grid

As of Nov 17, 2026

Which US grid has the most generation capacity in its interconnection queue? Of the 7 US grid operators whose generation interconnection queues DC Hub reads, ERCOT (Texas) has the most active generation capacity waiting: 461.4 GW as of Oct 31, 2026. Next are PJM at 373.5 GW as of Nov 17, 2026 (feed read date) and MISO at 259.6 GW as of Nov 17, 2026 (feed read date). Each figure carries its own date and the dates differ, so the order compares readings from different days; the queues are separate lists and are not added together. ERCOT's large-load queue (about 474 GW, June 2026 data) is a separate demand queue and is not in this ordering.

Active generation interconnection queue by US grid operator

Active generation requests in each ISO's own queue, as DC Hub last read it. A queue measures requests for grid access, not spare capacity, and it is not a forecast of what will be built. Each row has its own date; rows are ordered by GW and never summed. Alberta's, Ontario's and Great Britain's connection queues mix generation and demand projects, so they are not in this table.

Grid operatorActive generation queueAs ofWhat the date isSource
ERCOT (Texas)461.4 GWOct 31, 2026date of ERCOT's published reportERCOT GIS Report, October 2026 (posted 2026-11-02), Summary sheet
PJM (Mid-Atlantic and Midwest)373.5 GWNov 17, 2026the day DC Hub read PJM's live queue feed, which publishes no report datePJM cycle + serial service request status (active generation requests, sum of MFO)
MISO (Midcontinent)259.6 GWNov 17, 2026the day DC Hub read MISO's live queue feed, which publishes no report dateMISO GI Queue API (applicationStatus=Active, summer MW)
SPP (Central US)185.2 GWNov 17, 2026the day DC Hub read SPP's live queue feed, which publishes no report dateSPP GI active requests (MAX Summer MW, excl. cessation)
CAISO (California)164.8 GWJul 16, 2026date of the oldest of the 3 source files the figure sumsCAISO queue reports: Public Queue Report (ACTIVE, Net MWs to Grid) + Cluster 15 + Cluster 16 (NET MW POI)
ISO-NE (New England)10.9 GWNov 17, 2026the day DC Hub read ISO-NE's live queue feed, which publishes no report dateISO-NE IRTT Public Queue (active, Summer MW)
NYISO (New York)9.9 GWNov 13, 2026date of the source fileNYISO Interconnection Queue (active, SP MW)

Source: each ISO's own queue data via DC Hub (dchub.cloud/interconnection-queues).

ERCOT large-load queue (separate, not ranked)

Large loads, such as data centers, asking ERCOT to connect. This is a demand queue, not a generation queue, so it is not compared with or added to the rows above.

ItemValue and date
ERCOT large loads seeking interconnectionabout 474 GW (June 2026 data); about 90% of them data centers by ERCOT's own figure. Source: ERCOT Senate presentation, Jul 29, 2026

What this page does not state

Sources and citing

Source: DC Hub (dchub.cloud), as of Nov 17, 2026. Upstream: ERCOT GIS Report, October 2026 (posted 2026-11-02), Summary sheet; PJM cycle + serial service request status (active generation requests, sum of MFO); MISO GI Queue API (applicationStatus=Active, summer MW); SPP GI active requests (MAX Summer MW, excl. cessation); CAISO queue reports: Public Queue Report (ACTIVE, Net MWs to Grid) + Cluster 15 + Cluster 16 (NET MW POI); ISO-NE IRTT Public Queue (active, Summer MW); NYISO Interconnection Queue (active, SP MW); ERCOT Large Load Working Group and Senate presentation.

Cite as: DC Hub (dchub.cloud), "US interconnection queues by grid", https://dchub.cloud/answers/us-interconnection-queues-by-grid, as of Nov 17, 2026. Every figure is read from DC Hub's live data when this page is built; each carries its own date, and the page date is the newest of them.