Alberta and Ontario grid queue demand
As of Nov 17, 2026
How much data center demand is in Alberta's and Ontario's grid connection queues? DC Hub does not publish a figure for data centers alone in Alberta's or Ontario's grid connection queues: it tracks every demand (load) project in each queue, data centers included. AESO's queue (Alberta) holds 21.6 GW of demand projects out of 27.6 GW (78%), as of Nov 17, 2026 (feed read date). IESO's queue (Ontario) holds 12.5 GW of demand projects out of 19.1 GW (65.8%), as of Nov 17, 2026 (feed read date). These queues list generation and demand together, so they are not comparable with US generation interconnection queues and are never added to them.
Alberta and Ontario connection queues
These are connection queues: each lists generation and demand projects together. They are not generation queues, so they are not compared with or added to US generation interconnection queues. DC Hub's demand figure counts every demand (load) project in the queue, data centers included; it does not split data centers out.
| Grid operator | Demand projects in queue | Whole connection queue (generation and demand) | Demand share of the queue | As of | What the date is | Source |
|---|---|---|---|---|---|---|
| AESO (Alberta) | 21.6 GW | 27.6 GW | 78% | Nov 17, 2026 | the day DC Hub read AESO's live queue feed, which publishes no report date | Alberta AESO Connection Project List (active; November-2026-Project-List.xlsx) |
| IESO (Ontario) | 12.5 GW | 19.1 GW | 65.8% | Nov 17, 2026 | the day DC Hub read IESO's live queue feed, which publishes no report date | Ontario IESO CAA connection queue (active, summer MW) |
Source: each operator's own connection queue data via DC Hub (dchub.cloud/interconnection-queues).
Great Britain, for context
NESO's connections queue is also a mixed generation and demand list, read the same way. It is shown for context and is not added to the rows above.
| Grid operator | Demand projects in queue | Whole connection queue (generation and demand) | Demand share of the queue | As of | What the date is | Source |
|---|---|---|---|---|---|---|
| NESO (Great Britain) | 53.0 GW | 592.1 GW | 8.9% | Nov 17, 2026 | the day DC Hub read NESO's live queue feed, which publishes no report date | UK NESO TEC Register (active connections queue, per-project MW) |
What this page does not state
- A figure for data centers alone in either queue. DC Hub's demand figure is every demand (load) project in the queue; data centers are not split out, so this page states no data-center share.
- Any comparison with, or sum including, a US generation interconnection queue.
Sources and citing
Source: DC Hub (dchub.cloud), as of Nov 17, 2026. Upstream: Alberta AESO Connection Project List (active; November-2026-Project-List.xlsx); Ontario IESO CAA connection queue (active, summer MW); UK NESO TEC Register (active connections queue, per-project MW).
Cite as: DC Hub (dchub.cloud), "Alberta and Ontario grid queue demand", https://dchub.cloud/answers/alberta-ontario-grid-queue-data-center-demand, as of Nov 17, 2026. Every figure is read from DC Hub's live data when this page is built; each carries its own date, and the page date is the newest of them.
Related
- How much data center demand is in Alberta's and Ontario's grid connection queues?
- All interconnection queues (dchub.cloud/interconnection-queues)
- US generation interconnection queues by grid operator
- All DC Hub answers
Query this live from an AI agent: claude mcp add dchub --transport http https://dchub.cloud/mcp