Which US grid has the most generation capacity in its interconnection queue?

Of the 7 US grid operators whose generation interconnection queues DC Hub reads, ERCOT (Texas) has the most active generation capacity waiting: 461.4 GW as of Oct 31, 2026. Next are PJM at 373.5 GW as of Nov 17, 2026 (feed read date) and MISO at 259.6 GW as of Nov 17, 2026 (feed read date). Each figure carries its own date and the dates differ, so the order compares readings from different days; the queues are separate lists and are not added together. ERCOT's large-load queue (about 474 GW, June 2026 data) is a separate demand queue and is not in this ordering.

ERCOT (Texas)461.4 GW active generation queue, as of Oct 31, 2026
PJM (Mid-Atlantic and Midwest)373.5 GW active generation queue, as of Nov 17, 2026 (feed read date)
MISO (Midcontinent)259.6 GW active generation queue, as of Nov 17, 2026 (feed read date)
SPP (Central US)185.2 GW active generation queue, as of Nov 17, 2026 (feed read date)
CAISO (California)164.8 GW active generation queue, as of Jul 16, 2026
ISO-NE (New England)10.9 GW active generation queue, as of Nov 17, 2026 (feed read date)
NYISO (New York)9.9 GW active generation queue, as of Nov 13, 2026
ERCOT large-load queue (separate, not ranked)about 474 GW (June 2026 data), a demand queue

Source: DC Hub (dchub.cloud), as of Nov 17, 2026. Upstream: ERCOT GIS Report, October 2026 (posted 2026-11-02), Summary sheet; PJM cycle + serial service request status (active generation requests, sum of MFO); MISO GI Queue API (applicationStatus=Active, summer MW); SPP GI active requests (MAX Summer MW, excl. cessation); CAISO queue reports: Public Queue Report (ACTIVE, Net MWs to Grid) + Cluster 15 + Cluster 16 (NET MW POI); ISO-NE IRTT Public Queue (active, Summer MW); NYISO Interconnection Queue (active, SP MW); ERCOT Large Load Working Group and Senate presentation.

Cite as: DC Hub (dchub.cloud), "Which US grid has the most generation capacity in its interconnection queue?", https://dchub.cloud/ai-answers/us-interconnection-queues-by-grid, as of Nov 17, 2026.