Senate permitting bill and data center grid connections

As of Nov 23, 2026

What does the Senate permitting bill mean for data center grid connections? On Nov 19, 2026, the US Senate passed the Bipartisan American Affordability and Jobs Act (BAAJA), a permitting bill, 62 to 33. It goes to the House next and is not law. Analyses of the Senate text describe a new Federal Power Act section, carried out by FERC, under which large new loads such as data centers would pay the incremental cost of the grid infrastructure built to serve them. Those analyses disagree on the size threshold, so this page states none. The connections it would price wait in the grid operators' queues, and DC Hub reads each one with its own date. Of the 7 US grid operators whose generation interconnection queues DC Hub reads, ERCOT (Texas) has the most active generation capacity waiting: 461.4 GW as of Oct 31, 2026. Next are PJM at 373.2 GW as of Nov 23, 2026 (feed read date) and MISO at 253.4 GW as of Nov 23, 2026 (feed read date). Each figure carries its own date and the dates differ, so the order compares readings from different days; the queues are separate lists and are not added together. ERCOT's large-load queue (about 474 GW, June 2026 data) is a separate demand queue and is not in this ordering.

The Senate vote (as reported)

What the Senate passed and what analyses of its text say about data center grid costs. Not a DC Hub figure.

ItemValue and date
What was filed or votedThe US Senate passed the Bipartisan American Affordability and Jobs Act (BAAJA), a permitting bill, 62 to 33. It goes to the House next and is not law. (Nov 19, 2026)
StatusAnalyses of the Senate text describe a new Federal Power Act section, carried out by FERC, under which large new loads such as data centers would pay the incremental cost of the grid infrastructure built to serve them. Those analyses disagree on the size threshold, so this page states none.

Sources: CBS News, Senate passes bipartisan permitting reform bill, Nov 19, 2026; Foley Hoag, BAAJA Blast Part 3: data centers and large loads under the Senate permitting bill; White & Case, Senate permitting bill bolsters data center provisions.

Active generation interconnection queue by US grid operator

Active generation requests in each ISO's own queue, as DC Hub last read it. A queue measures requests for grid access, not spare capacity, and it is not a forecast of what will be built. Each row has its own date; rows are ordered by GW and never summed. Alberta's, Ontario's and Great Britain's connection queues mix generation and demand projects, so they are not in this table.

Grid operatorActive generation queueAs ofWhat the date isSource
ERCOT (Texas)461.4 GWOct 31, 2026date of ERCOT's published reportERCOT GIS Report, October 2026 (posted 2026-11-02), Summary sheet
PJM (Mid-Atlantic and Midwest)373.2 GWNov 23, 2026the day DC Hub read PJM's live queue feed, which publishes no report datePJM cycle + serial service request status (active generation requests, sum of MFO)
MISO (Midcontinent)253.4 GWNov 23, 2026the day DC Hub read MISO's live queue feed, which publishes no report dateMISO GI Queue API (applicationStatus=Active, summer MW)
SPP (Central US)185.5 GWNov 23, 2026the day DC Hub read SPP's live queue feed, which publishes no report dateSPP GI active requests (MAX Summer MW, excl. cessation)
CAISO (California)164.8 GWJul 16, 2026date of the oldest of the 3 source files the figure sumsCAISO queue reports: Public Queue Report (ACTIVE, Net MWs to Grid) + Cluster 15 + Cluster 16 (NET MW POI)
NYISO (New York)9.9 GWNov 13, 2026date of the source fileNYISO Interconnection Queue (active, SP MW)
ISO-NE (New England)9.5 GWNov 23, 2026the day DC Hub read ISO-NE's live queue feed, which publishes no report dateISO-NE IRTT Public Queue (active, Summer MW)

Source: each ISO's own queue data via DC Hub (dchub.cloud/interconnection-queues).

ERCOT large-load queue (separate, not ranked)

Large loads, such as data centers, asking ERCOT to connect. This is a demand queue, not a generation queue, so it is not compared with or added to the rows above.

ItemValue and date
ERCOT large loads seeking interconnectionabout 474 GW (June 2026 data); about 90% of them data centers by ERCOT's own figure. Source: ERCOT Senate presentation, Jul 29, 2026

What this page does not state

Sources and citing

Source: DC Hub (dchub.cloud), as of Nov 23, 2026. Upstream: CBS News, Senate passes bipartisan permitting reform bill, Nov 19, 2026; Foley Hoag, BAAJA Blast Part 3: data centers and large loads under the Senate permitting bill; White & Case, Senate permitting bill bolsters data center provisions; ERCOT GIS Report, October 2026 (posted 2026-11-02), Summary sheet; PJM cycle + serial service request status (active generation requests, sum of MFO); MISO GI Queue API (applicationStatus=Active, summer MW); SPP GI active requests (MAX Summer MW, excl. cessation); CAISO queue reports: Public Queue Report (ACTIVE, Net MWs to Grid) + Cluster 15 + Cluster 16 (NET MW POI); NYISO Interconnection Queue (active, SP MW); ISO-NE IRTT Public Queue (active, Summer MW); ERCOT Large Load Working Group and Senate presentation.

Cite as: DC Hub (dchub.cloud), "Senate permitting bill and data center grid connections", https://dchub.cloud/answers/senate-permitting-bill-data-center-grid-connections, as of Nov 23, 2026. Every figure is read from DC Hub's live data when this page is built; each carries its own date, and the page date is the newest of them.