Paying for grid upgrades to connect sooner

As of Nov 23, 2026

Can a data center pay to get grid power sooner? It can be proposed, and it has to be approved. On Nov 19, 2026, Google and Ohio Power Company (AEP Ohio) jointly filed a proposal with the Public Utilities Commission of Ohio (PUCO) under which Google would fund the full incremental cost of advanced conductors on 15.5 miles of aging transmission lines in Columbus. The parties say this would deliver 24 MW of capacity Google has already contracted for about two years early. The filing is pending: it needs approval from PUCO and the Ohio Power Siting Board; if approved, the upgrade is expected in service by late 2028. For the market around it, DC Hub's Data Center Power Index (DCPI) rates Columbus AVOID (last changed Nov 14, 2026) and New Albany AVOID (last changed Nov 1, 2026) for new data-center power, with a modelled time to power for Columbus of over 48 months (a model band, not a utility date). A funded upgrade shortens the wait where that upgrade is what holds the load back; the DCPI reading is market-wide and does not include this filing.

The Columbus filing (as reported by the parties)

A large load funding a transmission upgrade so that its own contracted capacity arrives sooner. This is the parties' description of their filing, not a DC Hub figure.

ItemValue and date
What was filed or votedGoogle and Ohio Power Company (AEP Ohio) jointly filed a proposal with the Public Utilities Commission of Ohio (PUCO) under which Google would fund the full incremental cost of advanced conductors on 15.5 miles of aging transmission lines in Columbus. The parties say this would deliver 24 MW of capacity Google has already contracted for about two years early. (Nov 19, 2026)
StatusThe filing is pending: it needs approval from PUCO and the Ohio Power Siting Board; if approved, the upgrade is expected in service by late 2028.

Source: Google and Ohio Power Company joint announcement, Nov 19, 2026.

DCPI verdicts for Columbus and New Albany

The verdict is DC Hub's Data Center Power Index (DCPI) reading for new data-center power: BUILD, CAUTION or AVOID. It describes the outlook for new power in the market, not the market's quality or size. The time to power is a modelled band, not a utility date. Each row is dated the day its verdict or scores last changed.

MarketDCPI verdictModelled time to power (band)Verdict and scores last changed
ColumbusAVOIDover 48 monthsNov 14, 2026
New AlbanyAVOIDover 48 monthsNov 1, 2026

Source: DC Hub Data Center Power Index (DCPI).

Grid operator queue

Columbus is in PJM. A queue measures requests for grid access; it is not spare capacity and it is not a forecast of what will be built.

ItemValue and date
PJM generation interconnection queue373.2 GW as of Nov 23, 2026. Source: PJM cycle + serial service request status (active generation requests, sum of MFO)

What this page does not state

Sources and citing

Source: DC Hub (dchub.cloud), as of Nov 23, 2026. Upstream: Google and Ohio Power Company joint announcement, Nov 19, 2026; DC Hub Data Center Power Index (DCPI); PJM cycle + serial service request status (active generation requests, sum of MFO).

Cite as: DC Hub (dchub.cloud), "Paying for grid upgrades to connect sooner", https://dchub.cloud/answers/pay-for-grid-upgrades-to-connect-sooner, as of Nov 23, 2026. Every figure is read from DC Hub's live data when this page is built; each carries its own date, and the page date is the newest of them.