Paying for grid upgrades to connect sooner
As of Nov 23, 2026
Can a data center pay to get grid power sooner? It can be proposed, and it has to be approved. On Nov 19, 2026, Google and Ohio Power Company (AEP Ohio) jointly filed a proposal with the Public Utilities Commission of Ohio (PUCO) under which Google would fund the full incremental cost of advanced conductors on 15.5 miles of aging transmission lines in Columbus. The parties say this would deliver 24 MW of capacity Google has already contracted for about two years early. The filing is pending: it needs approval from PUCO and the Ohio Power Siting Board; if approved, the upgrade is expected in service by late 2028. For the market around it, DC Hub's Data Center Power Index (DCPI) rates Columbus AVOID (last changed Nov 14, 2026) and New Albany AVOID (last changed Nov 1, 2026) for new data-center power, with a modelled time to power for Columbus of over 48 months (a model band, not a utility date). A funded upgrade shortens the wait where that upgrade is what holds the load back; the DCPI reading is market-wide and does not include this filing.
The Columbus filing (as reported by the parties)
A large load funding a transmission upgrade so that its own contracted capacity arrives sooner. This is the parties' description of their filing, not a DC Hub figure.
| Item | Value and date |
|---|---|
| What was filed or voted | Google and Ohio Power Company (AEP Ohio) jointly filed a proposal with the Public Utilities Commission of Ohio (PUCO) under which Google would fund the full incremental cost of advanced conductors on 15.5 miles of aging transmission lines in Columbus. The parties say this would deliver 24 MW of capacity Google has already contracted for about two years early. (Nov 19, 2026) |
| Status | The filing is pending: it needs approval from PUCO and the Ohio Power Siting Board; if approved, the upgrade is expected in service by late 2028. |
Source: Google and Ohio Power Company joint announcement, Nov 19, 2026.
DCPI verdicts for Columbus and New Albany
The verdict is DC Hub's Data Center Power Index (DCPI) reading for new data-center power: BUILD, CAUTION or AVOID. It describes the outlook for new power in the market, not the market's quality or size. The time to power is a modelled band, not a utility date. Each row is dated the day its verdict or scores last changed.
| Market | DCPI verdict | Modelled time to power (band) | Verdict and scores last changed |
|---|---|---|---|
| Columbus | AVOID | over 48 months | Nov 14, 2026 |
| New Albany | AVOID | over 48 months | Nov 1, 2026 |
Source: DC Hub Data Center Power Index (DCPI).
Grid operator queue
Columbus is in PJM. A queue measures requests for grid access; it is not spare capacity and it is not a forecast of what will be built.
| Item | Value and date |
|---|---|
| PJM generation interconnection queue | 373.2 GW as of Nov 23, 2026. Source: PJM cycle + serial service request status (active generation requests, sum of MFO) |
What this page does not state
- The amount paid. The parties' announcement states it; this page states no prices.
- Whether PUCO and the Ohio Power Siting Board approve the filing. This page records the filing as of Nov 19, 2026 and does not track the docket.
- A time to power for any one Columbus site. The DCPI band is a market-wide model, not a utility date.
- Similar agreements with other utilities. DC Hub does not track them.
Sources and citing
Source: DC Hub (dchub.cloud), as of Nov 23, 2026. Upstream: Google and Ohio Power Company joint announcement, Nov 19, 2026; DC Hub Data Center Power Index (DCPI); PJM cycle + serial service request status (active generation requests, sum of MFO).
Cite as: DC Hub (dchub.cloud), "Paying for grid upgrades to connect sooner", https://dchub.cloud/answers/pay-for-grid-upgrades-to-connect-sooner, as of Nov 23, 2026. Every figure is read from DC Hub's live data when this page is built; each carries its own date, and the page date is the newest of them.
Related
- Can a data center pay to get grid power sooner?
- Columbus DCPI breakdown
- Columbus market page
- How long does it take to get power for a new large load in Columbus?
- What does the Senate permitting bill mean for data center grid connections?