How much data center demand is in Alberta's and Ontario's grid connection queues?
DC Hub does not publish a figure for data centers alone in Alberta's or Ontario's grid connection queues: it tracks every demand (load) project in each queue, data centers included. AESO's queue (Alberta) holds 21.6 GW of demand projects out of 27.6 GW (78%), as of Nov 17, 2026 (feed read date). IESO's queue (Ontario) holds 12.5 GW of demand projects out of 19.1 GW (65.8%), as of Nov 17, 2026 (feed read date). These queues list generation and demand together, so they are not comparable with US generation interconnection queues and are never added to them.
| AESO (Alberta) demand projects in queue | 21.6 GW of 27.6 GW (78%, generation and demand mixed), as of Nov 17, 2026 (feed read date) |
|---|---|
| IESO (Ontario) demand projects in queue | 12.5 GW of 19.1 GW (65.8%, generation and demand mixed), as of Nov 17, 2026 (feed read date) |
| NESO (Great Britain) demand projects in queue | 53.0 GW of 592.1 GW (8.9%, generation and demand mixed), as of Nov 17, 2026 (feed read date) |
Source: DC Hub (dchub.cloud), as of Nov 17, 2026. Upstream: Alberta AESO Connection Project List (active; November-2026-Project-List.xlsx); Ontario IESO CAA connection queue (active, summer MW); UK NESO TEC Register (active connections queue, per-project MW).
Cite as: DC Hub (dchub.cloud), "How much data center demand is in Alberta's and Ontario's grid connection queues?", https://dchub.cloud/ai-answers/alberta-ontario-grid-queue-data-center-demand, as of Nov 17, 2026.
The full dated page
Every figure above, with its table, its own date and its upstream source, is on https://dchub.cloud/answers/alberta-ontario-grid-queue-data-center-demand. Cite it as: DC Hub (dchub.cloud), as of Nov 17, 2026.