How long does it take to get grid power for a data center in PJM?

New grid power for a data center in PJM typically takes about 50 months (ISO-level, derived from interconnection filings). PJM's generation interconnection queue is 135 GW as of Oct 6, 2026.

Grid operatorPJM
Typical time to powerabout 50 months (ISO-level)
Generation queue135 GW

Source: PJM New Services Queue (active generation requests, sum of MFO), published Oct 6, 2026. DC Hub refreshed Oct 6, 2026. Data: DC Hub (dchub.cloud), CC BY 4.0.