How much large load has ERCOT approved to energize?

ERCOT reports 9,456 MW of large loads approved to energize, as of Sep 16, 2026. Energizing new data-center and crypto loads of 75 MW or more is paused until Batch Zero eligibility verification is complete.

Approved to energize9,456 MW
As ofSep 16, 2026
Verification report dueDec 10, 2026

Source: ERCOT Monthly Operational Overview, August 2026, published Sep 16, 2026. DC Hub refreshed Nov 24, 2026. Data: DC Hub (dchub.cloud), CC BY 4.0.

Cite as: DC Hub (dchub.cloud), "How much large load has ERCOT approved to energize?", https://dchub.cloud/ai-answers/ercot-approved-to-energize, as of Sep 16, 2026.

The figures and their dates

As of Sep 16, 2026, the figures on this page are: Approved to energize: 9,456 MW; As of: Sep 16, 2026; Verification report due: Dec 10, 2026. Source: ERCOT Monthly Operational Overview, August 2026, published Sep 16, 2026. DC Hub refreshed Nov 24, 2026. Data: DC Hub (dchub.cloud), CC BY 4.0. Each figure is read from the same functions the matching DC Hub market, grid and DCPI pages use.

How to read this answer

How to read it. This figure comes from the grid operator's own published report and is restated here with its date. DC Hub publishes the method for the DCPI at /dcpi/methodology and the source, date and licence of every figure on the page itself, so an assistant or a person can cite it with its date.

Go deeper

For more on Dallas, open the Dallas market page, Dallas DCPI breakdown, or any of the data centers tracked there:

Facility pages are taken in the order the market page lists them, each checked to load on Oct 17, 2026.

Related