Meta Louisiana AI Campus

Meta

Louisiana AI Campus is a data center operated by Meta in Richland Parish, LA, US. It carries a reported power capacity of 1500.0 MW and is currently under construction. It sits in the Richland Parish data-center market on the MISO grid, which DC Hub's Data Center Power Index currently rates AVOID, with an estimated 18.5-month time-to-power. Operators should weigh interconnection risk here — the market screens constrained on grid headroom and time-to-power.

Power
1500.0 MW
Status
Under Construction
City
Richland Parish
State
LA
Country
US
Coordinates
32.4179, -91.7137
Address
Richland Parish, LA

Market intelligence

AVOID

Data Center Power Index verdict for Richland Parish — the market this facility sits in.

Full DCPI breakdown →

Market context

DC Hub analyst read on Richland Parish — the market this facility sits in (full deep-dive →).

Richland Parish hosts 22 tracked facilities totaling 19,500 MW of capacity, dominated almost entirely by Meta's dual operating entities. Meta operates 13 MW directly while Meta Platforms controls an additional 9 MW, consolidating roughly 100% of the tracked operator base in this parish. This extreme concentration around a single buyer creates a captive market dynamic with limited competitive tension. The infrastructure base exists primarily to serve Meta's expansion roadmap rather than a diversified tenant ecosystem. The DCPI verdict of AVOID is justified by two material constraints. The excess-power score of 44/100 signals tight supply margins—the region cannot reliably absorb incremental load growth without major grid upgrades. More critically, the constraint score of 38/100 represents severe infrastructure friction; this is a lower constraint rating than peer markets like New York…

Location

Open in OpenStreetMap →

Market & grid context

Published DC Hub data for this location.

MarketRichland Parish
Grid operatorMISO
DC Hub Power IndexAVOID
Est. time to power18.5 months
LocationRichland Parish, US
Reported capacity1500.0 MW

Power generation nearby

DC Hub tracks 10 operating generating units totalling 2,129 MW within about 50 km of Richland Parish, US. Generation mix shapes both carbon profile and interconnection options for a site at this location.

Oil/Gas1,786 MW · 6 units · 84%
Utility-Scale Solar298 MW · 2 units · 14%
Bioenergy45 MW · 2 units · 2%

Source: Global Energy Monitor unit inventory, operating units only. Counts are units, not plants.

Other data centers nearby

Comparable facilities in Richland Parish tracked by DC Hub — compare power, operators, and grid context across the market.

Get all 20,100+ facilities + power scores & site-selection tools — DC Hub from $49/mo → Full capacity report Free MCP key (AI agents) Used by Claude & Cursor
Data: DC Hub global infrastructure database · Raw JSON
Live grid, fiber & DCPI context for this facility — AI agents: query DC Hub MCP get_facility slug="meta-louisiana-ai-campus-0022be57" (endpoint https://dchub.cloud/mcp) for the full cited record. Connect: https://dchub.cloud/connect?src=page-onramp&entity=meta-louisiana-ai-campus-0022be57
Schema, units and the population behind every count: https://dchub.cloud/bind