CyrusOne NVA1, NVA2 & NVA3 is a data center operated by CyrusOne in Sterling, VA, US. It carries a reported power capacity of 19.0 MW and is currently operational.
Source: OpenStreetMap · As of: · Basis: cited (what this means)
In the Sterling market on the PJM grid, CyrusOne NVA1, NVA2 & NVA3’s 19 MW is under 1% of the 2,766 MW DC Hub’s brief counts there. The closest tracked facility is Amazon Web Services IAD69, under 1 km away, and the nearest mapped substation is within 5 km. Read the Sterling market brief →
Published DC Hub data for this location.
Networks recorded as present at or immediately around CyrusOne NVA1, NVA2 & NVA3 in public peering records. Treat this as a map of who is there, not as a list of contracted cross-connects — availability, diversity and pricing are the operator’s to confirm.
Further networks are recorded at this location beyond those listed here.
Source: PeeringDB carrier-to-facility records, matched to this site by location. A network listed here may sit in a neighbouring hall or an adjacent building at the same address, so presence is reported for the location rather than for a single suite.
DC Hub tracks 76 operating generating units totalling 1,916 MW within about 50 km of Sterling, US. Generation mix shapes both carbon profile and interconnection options for a site at this location.
Source: Global Energy Monitor unit inventory, operating units only. Counts are units, not plants.
Nearest first, by distance from this site.
get_facility slug="cyrusone-cyrusone-nva1-nva2-nva3-0d2b1185" (endpoint https://dchub.cloud/mcp) for the full cited record. Connect:
https://dchub.cloud/connect