Northern Virginia data center power
As of Nov 17, 2026
Is grid power available for a data center in Northern Virginia? DC Hub's Data Center Power Index rates Ashburn AVOID for new data-center power, as of Nov 4, 2026, with a modelled time to power of over 48 months (a model band, not a utility date). Across the 6 Northern Virginia markets DC Hub scores, the verdicts are 6 AVOID. PJM's published generation interconnection queue is 373.5 GW as of Nov 17, 2026. Figures as of Nov 17, 2026.
DCPI verdicts across Northern Virginia
The verdict is DC Hub's Data Center Power Index (DCPI) reading for new data-center power: BUILD, CAUTION or AVOID. It describes the outlook for new power in the market, not the market's quality or size. The time to power is a modelled band, not a utility date. Each row is dated the day its verdict or scores last changed.
| Market | DCPI verdict | Modelled time to power (band) | Verdict and scores last changed |
|---|---|---|---|
| Ashburn | AVOID | over 48 months | Nov 4, 2026 |
| Sterling | AVOID | over 48 months | Nov 3, 2026 |
| Reston | AVOID | over 48 months | Nov 2, 2026 |
| Herndon | AVOID | over 48 months | Nov 2, 2026 |
| Manassas | AVOID | over 48 months | Nov 16, 2026 |
| Leesburg | AVOID | over 48 months | Nov 3, 2026 |
Source: DC Hub Data Center Power Index (DCPI).
Grid and utility facts
A queue measures requests for grid access. It is not spare capacity and it is not a forecast of what will be built.
| Item | Value and date |
|---|---|
| Grid operator | PJM Interconnection, as of Nov 18, 2026 |
| PJM generation interconnection queue | 373.5 GW as of Nov 17, 2026. Source: PJM cycle + serial service request status (active generation requests, sum of MFO) |
| Retail utilities serving the area | Dominion Energy Virginia, Northern Virginia Electric Cooperative (NOVEC) (named in no order; a site is served by whichever utility's territory it sits in), as of Sep 30, 2026 |
What this page does not state
- Available MW at any Northern Virginia substation or site. DC Hub does not publish utility capacity commitments, and this page states none.
Sources and citing
Source: DC Hub (dchub.cloud), as of Nov 17, 2026. Upstream: DC Hub Data Center Power Index (DCPI); PJM cycle + serial service request status (active generation requests, sum of MFO); Utility territory: Loudoun County's utilities page, NOVEC's about page and the Virginia SCC regulated-companies service map.
Cite as: DC Hub (dchub.cloud), "Northern Virginia data center power", https://dchub.cloud/answers/northern-virginia-data-center-power, as of Nov 17, 2026. Every figure is read from DC Hub's live data when this page is built; each carries its own date, and the page date is the newest of them.
Related
- Is grid power available for a data center in Northern Virginia?
- Ashburn DCPI breakdown
- Northern Virginia market page
- PJM grid
- How much power is available for a data center in Ashburn?
- All DC Hub answers
Query this live from an AI agent: claude mcp add dchub --transport http https://dchub.cloud/mcp