How long does it take to get power for a new large load in Santa Clara?

DC Hub's model puts the time to power for a new large load in Santa Clara at about 48 months, a model estimate and not a utility date, as of Nov 24, 2026. DC Hub's Data Center Power Index rates Santa Clara CAUTION for new data-center power, as of Nov 24, 2026.

MarketSanta Clara
Grid operator or balancing authorityCAISO
DCPI verdictCAUTION, composite score 44.2 of 100, as of Nov 24, 2026. Source: DC Hub Data Center Power Index (DCPI)
Modelled time to power, new large loadabout 48 months, a model estimate and not a utility date, as of Nov 24, 2026. Source: DC Hub Data Center Power Index (DCPI)
CAISO interconnection queue headline164.8 GW, summed from 3 source files; the oldest is dated Jul 16, 2026, so the total is no newer than that. File dates, newest first: publicqueuereport.xlsx Nov 22, 2026; cluster-16-queue-report.xlsx Oct 16, 2026; cluster-15-interconnection-requests.xlsx Jul 16, 2026. Source: CAISO queue reports: Public Queue Report (ACTIVE, Net MWs to Grid) + Cluster 15 + Cluster 16 (NET MW POI).
What DC Hub does not holdA utility's own service date for a specific site, which the serving utility sets after its studies.

Sources, each dated in the table above: DC Hub DCPI; CAISO queue reports: Public Queue Report (ACTIVE, Net MWs to Grid) + Cluster 15 + Cluster 16 (NET MW POI). Data: DC Hub (dchub.cloud), CC BY 4.0. No OpenStreetMap-derived layer is used on this page.

Cite as: DC Hub (dchub.cloud), "How long does it take to get power for a new large load in Santa Clara?", https://dchub.cloud/ai-answers/time-to-power-santa-clara, as of Nov 24, 2026.

How to read this

The time to power is a modelled estimate of how long a new large load takes to connect in this market. It is not a utility date: the serving utility sets a site's date after its own studies, and a site with an existing service point can be faster or slower. The Data Center Power Index verdict describes the outlook for new power in the market. The ISO figure, where shown, describes the whole grid operator.

DCPI is a daily score of where data centers can get grid power, across 300+ markets.

Methodology and citing

The method is published at /dcpi/methodology, and each figure above carries its own date and source. Cite the as-of date: DC Hub (dchub.cloud), as of Nov 24, 2026.