New grid power for a data center in NYISO typically takes about 31 months (ISO-level, derived from interconnection filings). NYISO's generation interconnection queue is 10 GW as of Oct 6, 2026.
| Grid operator | NYISO |
|---|---|
| Typical time to power | about 31 months (ISO-level) |
| Generation queue | 10 GW |
Source: NYISO Interconnection Queue (active, SP MW), published Oct 6, 2026. DC Hub refreshed Oct 6, 2026. Data: DC Hub (dchub.cloud), CC BY 4.0.