How long does it take to get grid power for a data center in ISO-NE?

New grid power for a data center in ISO-NE typically takes about 34 months (ISO-level, derived from interconnection filings). ISO-NE's generation interconnection queue is 14 GW as of Oct 6, 2026.

Grid operatorISO-NE
Typical time to powerabout 34 months (ISO-level)
Generation queue14 GW

Source: ISO-NE IRTT Public Queue (active, Summer MW), published Oct 6, 2026. DC Hub refreshed Oct 6, 2026. Data: DC Hub (dchub.cloud), CC BY 4.0.