New grid power for a data center in ISO-NE typically takes about 34 months (ISO-level, derived from interconnection filings). ISO-NE's generation interconnection queue is 14 GW as of Oct 6, 2026.
| Grid operator | ISO-NE |
|---|---|
| Typical time to power | about 34 months (ISO-level) |
| Generation queue | 14 GW |
Source: ISO-NE IRTT Public Queue (active, Summer MW), published Oct 6, 2026. DC Hub refreshed Oct 6, 2026. Data: DC Hub (dchub.cloud), CC BY 4.0.