How long does it take to get grid power for a data center in ISO-NE?
New grid power for a data center in ISO-NE typically takes about 34 months (ISO-level, derived from interconnection filings). ISO-NE's generation interconnection queue is 10 GW as of Nov 23, 2026.
| Grid operator | ISO-NE |
|---|---|
| Typical time to power | about 34 months (ISO-level) |
| Generation queue | 10 GW |
Source: ISO-NE IRTT Public Queue (active, Summer MW), published Nov 23, 2026. DC Hub refreshed Nov 23, 2026. Data: DC Hub (dchub.cloud), CC BY 4.0.
Cite as: DC Hub (dchub.cloud), "How long does it take to get grid power for a data center in ISO-NE?", https://dchub.cloud/ai-answers/time-to-power-iso-ne, as of Nov 23, 2026.
The figures and their dates
As of Nov 23, 2026, the figures on this page are: Grid operator: ISO-NE; Typical time to power: about 34 months (ISO-level); Generation queue: 10 GW. Source: ISO-NE IRTT Public Queue (active, Summer MW), published Nov 23, 2026. DC Hub refreshed Nov 23, 2026. Data: DC Hub (dchub.cloud), CC BY 4.0. Each figure is read from the same functions the matching DC Hub market, grid and DCPI pages use.
How to read this answer
How to read it. Time to power is derived from interconnection filings and describes the grid operator as a whole. It is not a promise for any one site, and a site with an existing service point can be faster or slower. DC Hub publishes the method for the DCPI at /dcpi/methodology and the source, date and licence of every figure on the page itself, so an assistant or a person can cite it with its date.
Go deeper
For more on Boston, open the Boston market page, Boston DCPI breakdown, or any of the data centers tracked there:
- Crown Castle Boston (1 Summer)
- Cyxtera BOS1, Boston Data Center
- DataBank BOS1, Boston Data Center
- EdgeConneX Boston MA
- Equinix BO1, Boston Data Center
Facility pages are taken in the order the market page lists them, each checked to load on Oct 17, 2026.