How much power is available for a data center in Santa Clara?

DC Hub rates Santa Clara CAUTION for new data-center power. CAISO's typical time to power is about 40 months (ISO-level, filings-derived), and its generation interconnection queue is 74 GW as of Oct 6, 2026.

MarketSanta Clara
DC Hub DCPI verdictCAUTION
Grid operatorCAISO
ISO typical time to powerabout 40 months (ISO-level)
ISO generation queue74 GW as of Oct 6, 2026

Source: DC Hub Data Center Power Index and ISO interconnection queue filings, published Oct 7, 2026. DC Hub refreshed Oct 6, 2026. Data: DC Hub (dchub.cloud), CC BY 4.0.