How much power is available for a data center in Chicago?

DC Hub rates Chicago AVOID for new data-center power. PJM's typical time to power is about 50 months (ISO-level, filings-derived), and its generation interconnection queue is 373 GW as of Nov 22, 2026.

MarketChicago
DC Hub DCPI verdictAVOID
Grid operatorPJM
ISO typical time to powerabout 50 months (ISO-level)
ISO generation queue373 GW as of Nov 22, 2026

Source: DC Hub Data Center Power Index and ISO interconnection queue filings, published Nov 22, 2026. DC Hub refreshed Nov 22, 2026. Data: DC Hub (dchub.cloud), CC BY 4.0.

Cite as: DC Hub (dchub.cloud), "How much power is available for a data center in Chicago?", https://dchub.cloud/ai-answers/power-availability-chicago, as of Nov 22, 2026.

The figures and their dates

As of Nov 22, 2026, the figures on this page are: Market: Chicago; DC Hub DCPI verdict: AVOID; Grid operator: PJM; ISO typical time to power: about 50 months (ISO-level); ISO generation queue: 373 GW as of Nov 22, 2026. Source: DC Hub Data Center Power Index and ISO interconnection queue filings, published Nov 22, 2026. DC Hub refreshed Nov 22, 2026. Data: DC Hub (dchub.cloud), CC BY 4.0. Each figure is read from the same functions the matching DC Hub market, grid and DCPI pages use.

How to read this answer

How to read it. The verdict is the Data Center Power Index (DCPI) for the market: BUILD, CAUTION or AVOID for new data-center power. The time to power and the queue size are ISO-level figures, so every market the same grid operator serves shows the same ones. DC Hub publishes the method for the DCPI at /dcpi/methodology and the source, date and licence of every figure on the page itself, so an assistant or a person can cite it with its date.

Go deeper

For more on Chicago, open the Chicago market page, Chicago DCPI breakdown, or any of the data centers tracked there:

Facility pages are taken in the order the market page lists them, each checked to load on Oct 17, 2026.