How much data center capacity (MW) is in Dallas?
Dallas has 2,166 MW operational, 1,375 MW under construction and 1,095 MW planned among the verified sites DC Hub lists that report capacity, as of Nov 24, 2026. Counting every tracked site that reports MW, including unverified directory listings, the total is about 7,017 MW. Both are floors: they sum only the sites that report their MW, and most do not.
| Market | Dallas |
|---|---|
| Operational (verified sites) | 2,166 MW |
| Under construction (verified sites) | 1,375 MW |
| Planned (verified sites) | 1,095 MW |
| Verified sites listed | 4,636 MW |
| All tracked sites that report MW | about 7,017 MW (floor) |
Source: DC Hub data center inventory, published Nov 24, 2026. DC Hub refreshed Nov 24, 2026. Data: DC Hub (dchub.cloud), CC BY 4.0.
Cite as: DC Hub (dchub.cloud), "How much data center capacity (MW) is in Dallas?", https://dchub.cloud/ai-answers/data-center-capacity-dallas, as of Nov 24, 2026.
The figures and their dates
As of Nov 24, 2026, the figures on this page are: Market: Dallas; Operational (verified sites): 2,166 MW; Under construction (verified sites): 1,375 MW; Planned (verified sites): 1,095 MW; Verified sites listed: 4,636 MW; All tracked sites that report MW: about 7,017 MW (floor). Source: DC Hub data center inventory, published Nov 24, 2026. DC Hub refreshed Nov 24, 2026. Data: DC Hub (dchub.cloud), CC BY 4.0. Each figure is read from the same functions the matching DC Hub market, grid and DCPI pages use.
How to read this answer
How to read it. The capacity figure sums only the sites that report their megawatts, so it is a floor. A market with several unreported sites is larger than the number shown. DC Hub publishes the method for the DCPI at /dcpi/methodology and the source, date and licence of every figure on the page itself, so an assistant or a person can cite it with its date.
Go deeper
For more on Dallas, open the Dallas market page, Dallas DCPI breakdown, or any of the data centers tracked there:
- Yondr Lancaster (Dallas Campus)
- DataBank Red Oak Mega Campus
- Anthropic Texas AI Campus
- Tallgrass Denton DC
- Compass Red Oak Campus (Dallas)
Facility pages are taken in the order the market page lists them, each checked to load on Oct 17, 2026.