| Operator | Facility | Power | Status | ETA |
|---|---|---|---|---|
| NRG Energy | NRG T.H. Wharton Data Center Power Site | 295 MW | Under Construction | Not tracked |
| ServerFarm | ServerFarm HTX2 Houston | 100 MW | Under Construction | Not tracked |
| ServerFarm | ServerFarm CTX2 Houston | 100 MW | Under Construction | Not tracked |
| Operator | Facilities | Total MW |
|---|---|---|
| CyrusOne | 5 | 95 MW |
| DataBank | 5 | 0 MW |
| ServerFarm | 4 | 500 MW |
| DataBank, Ltd. | 3 | 0 MW |
| Digital Realty Digital Houston Campus | 3 | 0 MW |
| Date | Buyer | Seller | Value | MW |
|---|---|---|---|---|
| Not tracked | Amazon | Not tracked | $10,000 | Not tracked |
| Not tracked | Amazon | Not tracked | $10,000 | Not tracked |
| Not tracked | I Squared Capital | Not tracked | $225 | Not tracked |
Houston's tracked data center footprint spans 97 facilities totaling 1,075 MW across operational, under-construction, and planned assets, but infrastructure constraints are beginning to outpace capacity growth. CyrusOne and DataBank each operate five facilities in the market, while ServerFarm operates four, creating a competitive but fragmented operator base. The market's recent deal activity centers on Amazon's two announced $10 billion investment commitments, though both remain subject to regulatory scrutiny and infrastructure feasibility questions that have not yet been resolved.
The DCPI verdict of CAUTION reflects balanced but tightening conditions: an excess-power score of 56/100 signals adequate near-term generation headroom, while the constraint score of 57/100 indicates transmission and interconnection bottlenecks are already constraining deployment velocity. For acquisition-focused investors, this score suggests Houston remains accessible but requires site-level due diligence on power routing and grid interconnection timelines. The paired scores indicate the market is neither in crisis nor wide-open; deals here demand specificity around utility commitments and load energization schedules rather than reliance on aggregate capacity narratives.
Deal flow into Houston reflects both bullish cloud-scale appetite and ground-level friction. Amazon's two $10 billion commitments, if completed, would represent the largest announced investments in the market, yet press coverage highlights regulatory headwinds and permitting delays that complicate realization. The I Squared Capital acquisition (valued at $225 million) and broader M&A interest from Aligned Data Centers suggest strategic buyers view Houston as a consolidation target, likely to capture operational scale and utility relationships. Unlike Douglasville, where deal flow remains minimal, Houston demonstrates continuous capital inflow, but unlike Austin's higher excess-power score of 65/100, Houston operators face more immediate grid constraints.
CenterPoint Energy's $1.2 billion investment plan to energize up to 8 GW of data center load by 2029 represents the critical supply-side variable: if realized, this would expand deployable capacity roughly 7.5x current tracked MW, materially shifting Houston from constrained to abundant. Until that infrastructure materializes and interconnection backlogs clear, investors should treat individual projects with skepticism and anchor valuations to utility-confirmed power availability rather than announced megawatt targets.