DC Hub rates Des Moines AVOID for new data-center power. MISO's typical time to power is about 34 months (ISO-level, filings-derived), and its generation interconnection queue is 239 GW as of Oct 6, 2026.
| Market | Des Moines |
|---|---|
| DC Hub DCPI verdict | AVOID |
| Grid operator | MISO |
| ISO typical time to power | about 34 months (ISO-level) |
| ISO generation queue | 239 GW as of Oct 6, 2026 |
Source: DC Hub Data Center Power Index and ISO interconnection queue filings, published Oct 7, 2026. DC Hub refreshed Oct 6, 2026. Data: DC Hub (dchub.cloud), CC BY 4.0.