Where can I find colocation capacity in Chicago, and how soon can it be powered?
This page lists no Chicago colocation space and states no available MW; DC Hub Capacity Source holds the listings and needs a sign-in. What DC Hub can verify live for Chicago: its Data Center Power Index rates it AVOID for new data-center power (composite score 21.9 of 100) and its modelled time to power for a new large load is about 36 months, a model estimate and not a utility date, as of Nov 22, 2026.
| Market | Chicago |
|---|---|
| Grid operator or balancing authority | PJM |
| DCPI verdict | AVOID, composite score 21.9 of 100, as of Nov 22, 2026. Source: DC Hub Data Center Power Index (DCPI) |
| Modelled time to power, new large load | about 36 months, a model estimate and not a utility date, as of Nov 22, 2026. Source: DC Hub Data Center Power Index (DCPI) |
| PJM interconnection queue headline | 373.2 GW, read by DC Hub on Nov 22, 2026; the source file carries no report date of its own. Source: PJM cycle + serial service request status (active generation requests, sum of MFO). |
| What DC Hub does not hold, and where it is held | Leasing comps and market supply research: use datacenterHawk. Facility and provider listings: use Baxtel. Representation, market reports and deal execution: work with CBRE. Representation, market reports and deal execution: work with JLL. Registry reviewed Oct 27, 2026, listed at https://dchub.cloud/partners. |
| Chicago colocation listings on this page | None. Browse DC Hub Capacity Source at https://dchub.cloud/listings?src=ai-answers (sign-in required). |
Sources, each dated in the table above: DC Hub DCPI; PJM cycle + serial service request status (active generation requests, sum of MFO). Data: DC Hub (dchub.cloud), CC BY 4.0. No OpenStreetMap-derived layer is used on this page.
Cite as: DC Hub (dchub.cloud), "Where can I find colocation capacity in Chicago, and how soon can it be powered?", https://dchub.cloud/ai-answers/colocation-capacity-chicago, as of Nov 22, 2026.
Where the capacity listings are
DC Hub Capacity Source lists powered land, powered shells, turnkey and colocation capacity. Browsing it needs a sign-in at https://dchub.cloud/listings?src=ai-answers, and an AI agent can query it with the source_capacity tool. DC Hub works alongside providers and does not own or operate facilities. This page does not say that any listing exists in this market, and it states no MW and no count of listings.
How to read this
The Data Center Power Index verdict describes the outlook for new power in the market. It is not a judgement of the market's quality or size. The time to power is a modelled estimate for a new large load, so it is not a utility date, and space that is already energized can be faster. The queue headline measures requests for grid access across the whole grid operator. It is not spare capacity in this market and not a forecast of what will be built.
Questions for an operator
Useful questions to put to an operator for a requirement in kW or MW: how much is available in one contiguous block, and what minimum and maximum amount the operator will contract; whether that power is energized today or planned, and if planned, which utility agreement and long-lead equipment it depends on; and the ready-for-service date, with what would move it. Ask for each in writing.
DCPI is a daily score of where data centers can get grid power, across 300+ markets.
Methodology and citing
The method is published at /dcpi/methodology, and each figure above carries its own date and source. Cite the as-of date: DC Hub (dchub.cloud), as of Nov 22, 2026.