# Paris data center market

Power availability in Paris: DCPI verdict AVOID, composite score 20.7 of 100, as of 2026-11-12. Source: DC Hub.

Data Center Market Deep-Dive · 228 words · generated 2026-11-10 from live DC Hub data · DCPI live as of 2026-11-12

**Question this page answers:** How much power is available in the Paris data center market?

**Answer it live over MCP:** `execute_plan(intent="how much power is available in the Paris market for a data center")`

**Cite as:** DC Hub (dchub.cloud), as of [the as_of date on the result].

DCPI Score**20.7/100**

MW, all listings**356**sum of the sites that report MW; most do notany status, unverified listings included

Verdict**AVOID**

## Paris at a glance

Paris has 304 MW operational among the verified sites DC Hub lists that report capacity, as of 2026-11-12. By listed capacity the largest operators are Equinix (113 MW), Interxion (75 MW) and Digital Realty (40 MW).

Capacity by status, as of 2026-11-12

| Status | MW |
| --- | --- |
| Operational | 304 |
| Total listed | 304 |

Source: DC Hub (dchub.cloud), facility records as of 2026-11-12. Verified sites that report MW only; blank means no MW reported. The "MW, all listings" tile above is a wider measure (every tracked site that reports MW, any status, unverified directory listings included), so it is larger than Total listed.

## Colocation lease rates in Paris

Broker lease rates (CBRE/JLL): available on paid plans. Asking base rent per kW of critical IT capacity. Electricity is normally billed separately (metered pass-through), plus cross-connects and one-time fees. Signed deals, term and size change the number. Source: CBRE Global Data Center Trends 2026, Figure 5 (Monthly Pricing for 250-to-500-kW Capacity by Market, Q1 2026): Paris (figure on paid plans) [(link)](https://www.cbre.com/insights/reports/global-data-center-trends-2026)

The market shows no recorded deal announcements in the current tracking cycle, though Digital Realty has initiated groundbreaking activity on a new Paris facility.

This combination places Paris in the AVOID category for new power procurement, meaning operators pursuing capacity expansion face material delays in grid connection timelines and heightened cost exposure for infrastructure upgrades needed to support additional demand.

Deal flow in Paris remains dormant with no recent transactions recorded. The operator landscape remains stable, with Equinix and Digital Reality commanding the largest footprints. Recent groundbreaking by Digital Reality signals active site-level development, and a separate announcement flagged a large Nvidia Blackwell deployment at a Global Switch Paris facility, though the end-user remains undisclosed.

Forward-looking, power grid co-location dynamics will remain the primary friction point for Paris data center expansion through 2027.

## Data centers in Paris

| Facility | Operator | Status | MW |
| --- | --- | --- | --- |
| [Equinix PA Campus](https://dchub.cloud/facilities/equinix-equinix-pa-campus-2c371f34) | Equinix | Operational | 60 |
| [Global Switch](https://dchub.cloud/facilities/global-switch-global-switch-5b0f97c8) |  | Operational | 46 |
| [Interxion Paris](https://dchub.cloud/facilities/digital-realty-interxion-paris-e6345ee5) | Digital Realty | Operational | 40 |
| [Equinix PA4](https://dchub.cloud/facilities/equinix-equinix-pa4-7a236d13) | Equinix | Operational | 35 |
| [Interxion PAR8](https://dchub.cloud/facilities/interxion-interxion-par8-4b2b1532) | Interxion | Operational | 30 |
| [Interxion PAR7](https://dchub.cloud/facilities/interxion-interxion-par7-b643cafb) | Interxion | Operational | 25 |
| [Interxion PAR5](https://dchub.cloud/facilities/interxion-interxion-par5-6fc1ef3c) | Interxion | Operational | 20 |
| [Equinix PA13X](https://dchub.cloud/facilities/equinix-equinix-pa13x-12146dcc) | Equinix | Operational | 18 |
| [BNP Paribas Marne Sud](https://dchub.cloud/facilities/bnp-paribas-bnp-paribas-marne-sud-38ca6808) | BNP Paribas | Operational | 5 |
| [Datacenter EDF](https://dchub.cloud/facilities/edf-datacenter-edf-4cc28979) | EDF | Operational | 5 |
| [Datacenter RTE](https://dchub.cloud/facilities/rte-datacenter-rte-44af15aa) | RTE | Operational | 5 |
| [GTT](https://dchub.cloud/facilities/gtt-gtt-8d00ffa1) |  | Operational | 5 |
| [Orange - Aubervilliers](https://dchub.cloud/facilities/orange-orange-aubervilliers-a2bc8e0b) | Orange | Operational | 5 |
| [nLighten France](https://dchub.cloud/facilities/nlighten-france-nlighten-france-b2a08be4) |  | Operational | 5 |
| [AWS EU West 3 (Paris)](https://dchub.cloud/facilities/amazon-web-services-aws-eu-west-3-paris-0338da8f) | Amazon Web Services | Operational |  |
| [Alphalink Telco Center](https://dchub.cloud/facilities/alphalink-telco-center-alphalink-telco-center-dd2e983f) |  | Operational |  |
| [Azure France Central Paris](https://dchub.cloud/facilities/microsoft-azure-france-central-paris-2b208379) | Microsoft | Operational |  |
| [Bouygues Telecom Montigny-le-Bretonneux](https://dchub.cloud/facilities/bouygues-telecom-bouygues-telecom-montigny-le-bretonneux-58a7e2bf) | Bouygues Telecom | Operational |  |
| [Bâtiment Data Center](https://dchub.cloud/facilities/mbda-france-btiment-data-center-e951e03a) | MBDA France | Operational |  |
| [Datacenter](https://dchub.cloud/facilities/societe-technologie-exploitation-informatique-datacenter-13f9f323) | SOCIETE TECHNOLOGIE EXPLOITATION INFORMATIQUE | Operational |  |

Largest first by reported MW (blank where not reported). Unverified directory listings are not shown.

Browse every data center in [France](https://dchub.cloud/facilities/in/fr).

## More on Paris

- [Paris DCPI score](https://dchub.cloud/dcpi/paris)
- [Paris market brief](https://dchub.cloud/markets/paris/brief)

### Email me when the Paris DCPI verdict changes

Email me when Paris's DCPI verdict (BUILD / CAUTION / AVOID) changes. We'll send one confirmation link first; nothing else is sent unless you click it. Unsubscribe anytime.

Looking for an offer? [Find data center capacity to buy or lease](https://dchub.cloud/listings). Market facility totals describe tracked infrastructure, not currently authorized available offers. Check each listing’s scope, freshness, delivery schedule and operator approval.

Control a site or capacity? [List operator-controlled capacity for review](https://dchub.cloud/listings#list-capacity). DC Hub complements your existing research and procurement tools with data center and energy intelligence.

Ask your agent: connect [https://dchub.cloud/mcp](https://dchub.cloud/connect?ref=market-related) (no key needed for previews).

Paris: 356 MW tracked, any status — live, cited, and queryable by API or MCP.

[Unlock full market data →](https://dchub.cloud/pricing?ref=market-deep-dive&tool=paris) · [Get an API key →](https://dchub.cloud/connect?ref=market-deep-dive&tool=paris)

JSON: [/api/v1/markets/paris/deep-dive](https://dchub.cloud/api/v1/markets/paris/deep-dive) · DCPI: [/dcpi](https://dchub.cloud/dcpi) · Operators: [/operators](https://dchub.cloud/operators) · Narrative written 2026-11-10, refreshed on a rolling schedule (about monthly per market); the DCPI score, MW total and facility records above are read live at page load

```json
{"@context":"https://schema.org","@type":"BreadcrumbList","itemListElement":[{"@type":"ListItem","position":1,"name":"DC Hub","item":"https://dchub.cloud/"},{"@type":"ListItem","position":2,"name":"Markets","item":"https://dchub.cloud/markets"},{"@type":"ListItem","position":3,"name":"Paris","item":"https://dchub.cloud/markets/paris"}]}
{
 "@context":"https://schema.org","@type":"Article",
 "headline":"Paris Data Center Market Deep-Dive",
 "datePublished":"2026-11-10T09:02:17.329187+00:00",
 "author":{"@type":"Organization","@id":"https://dchub.cloud/#organization","name":"DC Hub","url":"https://dchub.cloud"},
 "publisher":{"@type":"Organization","@id":"https://dchub.cloud/#organization","name":"DC Hub","url":"https://dchub.cloud"},
 "url":"https://dchub.cloud/markets/paris",
 "wordCount":228,
 "about":{"@type":"Place","name":"Paris"},
 "description":"Live data-center market analysis. DCPI score 20.7/100."
}
{"@context": "https://schema.org", "@type": "Dataset", "identifier": "paris", "name": "Paris Data Center Market — DC Hub", "description": "Live data-center market measurements for Paris, published by DC Hub with the basis of each figure.", "url": "https://dchub.cloud/markets/paris", "license": "https://creativecommons.org/licenses/by/4.0/", "isAccessibleForFree": true, "creator": {"@type": "Organization", "@id": "https://dchub.cloud/#organization", "name": "DC Hub", "url": "https://dchub.cloud"}, "citation": "DC Hub, dchub.cloud", "spatialCoverage": {"@type": "Place", "name": "Paris"}, "variableMeasured": [{"@type": "PropertyValue", "name": "Total Capacity", "value": 356.0, "unitCode": "MAW", "unitText": "MW", "measurementTechnique": "collapse each site to one figure first (MAX(mw) per identity), then sum — immune to multi-row sites, but silently drops a genuinely separate building that shares an identity key", "description": "population=tracked; aggregation=sum_sites; grouping=market_slug — MW totals from different surfaces are comparable only when all three axes match. A larger number is usually a wider population, not more capacity. Definitions: https://dchub.cloud/data-sources"}, {"@type": "PropertyValue", "name": "DCPI Score", "value": 20.7, "maxValue": 100, "measurementTechnique": "Data Center Power Index — buildability composite scored 0-100 (excess-power headroom, grid constraint, time-to-power), verdict-gated. Comparable only against other DCPI scores; not a capacity, a ranking position, or a percentage.", "description": "Data Center Power Index — buildability composite, 0-100. Observed 2026-11-12T08:48:18."}, {"@type": "PropertyValue", "name": "DCPI Verdict", "value": "AVOID", "measurementTechnique": "Data Center Power Index verdict. One of BUILD, CAUTION, AVOID. Derived from exactly two inputs, the excess-power and grid-constraint scores: BUILD when excess-power ≥ 65 and grid-constraint ≤ 50; CAUTION when excess-power ≥ 50 and grid-constraint ≤ 70; otherwise AVOID. Time-to-power is NOT an input — a faster interconnect cannot move a market out of AVOID. AVOID is the fallback, so it means the market did not clear a band, including when an input is missing; it is not a claim that the market is actively bad. A label, not a score: not orderable and not comparable with a number. Observed 2026-11-12T08:48:18.", "description": "Data Center Power Index verdict. One of BUILD, CAUTION, AVOID. Derived from exactly two inputs, the excess-power and grid-constraint scores: BUILD when excess-power ≥ 65 and grid-constraint ≤ 50; CAUTION when excess-power ≥ 50 and grid-constraint ≤ 70; otherwise AVOID. Time-to-power is NOT an input — a faster interconnect cannot move a market out of AVOID. AVOID is the fallback, so it means the market did not clear a band, including when an input is missing; it is not a claim that the market is actively bad. A label, not a score: not orderable and not comparable with a number. Observed 2026-11-12T08:48:18."}], "dateModified": "2026-11-10", "temporalCoverage": "2026-11-10"}
{"@context": "https://schema.org", "@type": "WebPage", "@id": "https://dchub.cloud/markets/paris#webpage", "url": "https://dchub.cloud/markets/paris", "name": "Paris data center market", "mainEntity": {"@type": "Question", "name": "How much power is available in the Paris data center market?", "acceptedAnswer": {"@type": "Answer", "text": "Ask it live over MCP: execute_plan(intent=\"how much power is available in the Paris market for a data center\"). Cite as: DC Hub (dchub.cloud), as of [the as_of date on the result]."}}, "potentialAction": {"@type": "Action", "name": "How much power is available in the Paris data center market?", "description": "Ask this question live over MCP with execute_plan(intent=\"how much power is available in the Paris market for a data center\"). Cite as: DC Hub (dchub.cloud), as of [the as_of date on the result].", "target": {"@type": "EntryPoint", "urlTemplate": "https://dchub.cloud/mcp", "contentType": "application/json", "httpMethod": "POST"}}}
```