# Osaka data center market

Power availability in Osaka: DCPI verdict AVOID, composite score 18.7 of 100, as of 2026-11-12. Source: DC Hub.

Data Center Market Deep-Dive · 282 words · generated 2026-11-07 from live DC Hub data · DCPI live as of 2026-11-12

**Question this page answers:** How much power is available in the Osaka data center market?

**Answer it live over MCP:** `execute_plan(intent="how much power is available in the Osaka market for a data center")`

**Cite as:** DC Hub (dchub.cloud), as of [the as_of date on the result].

DCPI Score**18.7/100**

MW, all listings**130**sum of the sites that report MW; most do notany status, unverified listings included

Verdict**AVOID**

## Osaka at a glance

Osaka has 130 MW under construction among the verified sites DC Hub lists that report capacity, as of 2026-11-12. By listed capacity the largest operators are AirTrunk (100 MW) and STACK Infrastructure (30 MW).

Capacity by status, as of 2026-11-12

| Status | MW |
| --- | --- |
| Under construction | 130 |
| Total listed | 130 |

## Developers building or planning in Osaka

| Operator | Under construction MW | Planned MW |
| --- | --- | --- |
| AirTrunk | 100 |  |
| STACK Infrastructure | 30 |  |

Source: DC Hub (dchub.cloud), facility records as of 2026-11-12. Verified sites that report MW only; blank means no MW reported. The "MW, all listings" tile above is a wider measure (every tracked site that reports MW, any status, unverified directory listings included), so it is larger than Total listed.

## Colocation lease rates in Osaka

DC Hub does not hold a lease-rate figure for this market yet.

Digital Realty is constructing the 24 MW KIX15 facility in Osaka, underscoring continued deployment despite these conditions.

The DCPI verdict of AVOID reflects a supply-demand imbalance on the power side. Together, these metrics indicate that acquiring or building incremental capacity requires negotiating power supply agreements in a market where available grid headroom is limited. No recent tracked deals have materialized in Osaka, suggesting current commercial terms may not align with deployment urgency.

OPTAGE's five-site presence establishes the largest operational footprint, followed by Equinix and NTT DOCOMO BUSINESS at three sites each. The absence of recent deal activity—no acquisitions, stakes, or partnerships recorded—contrasts with broader Japan momentum, where CapitaLand has acquired Osaka data center assets from Mitsui, and Itochu plans ten new facilities nationally by 2030. Kansai, the broader region encompassing Osaka, has emerged as a secondary data center hub as primary markets saturate, yet Osaka itself has not captured corresponding M&A or greenfield announcement volume.

## Data centers in Osaka

| Facility | Operator | Status | MW |
| --- | --- | --- | --- |
| [AirTrunk OSK2 Osaka](https://dchub.cloud/facilities/airtrunk-airtrunk-osk2-osaka-7659797f) | AirTrunk | Under Construction | 100 |
| [STACK KIX01 Osaka](https://dchub.cloud/facilities/stack-infrastructure-stack-kix01-osaka-5a20f473) | STACK Infrastructure | Under Construction | 30 |
| [AWS AP Northeast 3 (Osaka)](https://dchub.cloud/facilities/amazon-web-services-aws-ap-northeast-3-osaka-1da5ccd6) | Amazon Web Services | Operational |  |
| [AirTrunk OSA1 Osaka](https://dchub.cloud/facilities/airtrunk-airtrunk-osa1-osaka-b1f1c400) | AirTrunk | Operational |  |
| [Azure Japan West Osaka](https://dchub.cloud/facilities/microsoft-azure-japan-west-osaka-362cac82) | Microsoft | Operational |  |
| [KAGOYA データセンター A棟](https://dchub.cloud/facilities/kagoya-a-d0340643) | カゴヤ・ジャパン株式会社 | Operational |  |
| [NTT DOCOMO BUSINESS OS4 - Osaka](https://dchub.cloud/facilities/ntt-docomo-business-data-centers-ntt-docomo-business-os4-osaka-818e7dee) | NTT DOCOMO BUSINESS (Data Centers) | Operational |  |
| [NTT Kitahama Data Center(Dojima Campus)](https://dchub.cloud/facilities/ntt-smartconnect-corporation-ntt-kitahama-data-centerdojima-campus-124e849d) | NTT SmartConnect Corporation | Operational |  |
| [OPTAGE – OC1（Sonezaki DC）](https://dchub.cloud/facilities/optage-inc-optage-oc1sonezaki-dc-0d2f5bc0) | OPTAGE Inc. | Operational |  |
| [Vantage Osaka Japan](https://dchub.cloud/facilities/vantage-data-centers-vantage-osaka-japan-912f109f) | Vantage Data Centers | Operational |  |

Largest first by reported MW (blank where not reported). Unverified directory listings are not shown.

Browse every data center in [Japan](https://dchub.cloud/facilities/in/jp).

## More on Osaka

- [Osaka DCPI score](https://dchub.cloud/dcpi/osaka)
- [Osaka market brief](https://dchub.cloud/markets/osaka/brief)

### Email me when the Osaka DCPI verdict changes

Email me when Osaka's DCPI verdict (BUILD / CAUTION / AVOID) changes. We'll send one confirmation link first; nothing else is sent unless you click it. Unsubscribe anytime.

Looking for an offer? [Find data center capacity to buy or lease](https://dchub.cloud/listings). Market facility totals describe tracked infrastructure, not currently authorized available offers. Check each listing’s scope, freshness, delivery schedule and operator approval.

Control a site or capacity? [List operator-controlled capacity for review](https://dchub.cloud/listings#list-capacity). DC Hub complements your existing research and procurement tools with data center and energy intelligence.

Ask your agent: connect [https://dchub.cloud/mcp](https://dchub.cloud/connect?ref=market-related) (no key needed for previews).

Osaka: 130 MW tracked, any status — live, cited, and queryable by API or MCP.

[Unlock full market data →](https://dchub.cloud/pricing?ref=market-deep-dive&tool=osaka) · [Get an API key →](https://dchub.cloud/connect?ref=market-deep-dive&tool=osaka)

JSON: [/api/v1/markets/osaka/deep-dive](https://dchub.cloud/api/v1/markets/osaka/deep-dive) · DCPI: [/dcpi](https://dchub.cloud/dcpi) · Operators: [/operators](https://dchub.cloud/operators) · Narrative written 2026-11-07, refreshed on a rolling schedule (about monthly per market); the DCPI score, MW total and facility records above are read live at page load

```json
{"@context":"https://schema.org","@type":"BreadcrumbList","itemListElement":[{"@type":"ListItem","position":1,"name":"DC Hub","item":"https://dchub.cloud/"},{"@type":"ListItem","position":2,"name":"Markets","item":"https://dchub.cloud/markets"},{"@type":"ListItem","position":3,"name":"Osaka","item":"https://dchub.cloud/markets/osaka"}]}
{
 "@context":"https://schema.org","@type":"Article",
 "headline":"Osaka Data Center Market Deep-Dive",
 "datePublished":"2026-11-07T09:16:35.760483+00:00",
 "author":{"@type":"Organization","@id":"https://dchub.cloud/#organization","name":"DC Hub","url":"https://dchub.cloud"},
 "publisher":{"@type":"Organization","@id":"https://dchub.cloud/#organization","name":"DC Hub","url":"https://dchub.cloud"},
 "url":"https://dchub.cloud/markets/osaka",
 "wordCount":282,
 "about":{"@type":"Place","name":"Osaka"},
 "description":"Live data-center market analysis. DCPI score 18.7/100."
}
{"@context": "https://schema.org", "@type": "Dataset", "identifier": "osaka", "name": "Osaka Data Center Market — DC Hub", "description": "Live data-center market measurements for Osaka, published by DC Hub with the basis of each figure.", "url": "https://dchub.cloud/markets/osaka", "license": "https://creativecommons.org/licenses/by/4.0/", "isAccessibleForFree": true, "creator": {"@type": "Organization", "@id": "https://dchub.cloud/#organization", "name": "DC Hub", "url": "https://dchub.cloud"}, "citation": "DC Hub, dchub.cloud", "spatialCoverage": {"@type": "Place", "name": "Osaka"}, "variableMeasured": [{"@type": "PropertyValue", "name": "Total Capacity", "value": 130.0, "unitCode": "MAW", "unitText": "MW", "measurementTechnique": "collapse each site to one figure first (MAX(mw) per identity), then sum — immune to multi-row sites, but silently drops a genuinely separate building that shares an identity key", "description": "population=tracked; aggregation=sum_sites; grouping=market_slug — MW totals from different surfaces are comparable only when all three axes match. A larger number is usually a wider population, not more capacity. Definitions: https://dchub.cloud/data-sources"}, {"@type": "PropertyValue", "name": "DCPI Score", "value": 18.7, "maxValue": 100, "measurementTechnique": "Data Center Power Index — buildability composite scored 0-100 (excess-power headroom, grid constraint, time-to-power), verdict-gated. Comparable only against other DCPI scores; not a capacity, a ranking position, or a percentage.", "description": "Data Center Power Index — buildability composite, 0-100. Observed 2026-11-12T08:48:20."}, {"@type": "PropertyValue", "name": "DCPI Verdict", "value": "AVOID", "measurementTechnique": "Data Center Power Index verdict. One of BUILD, CAUTION, AVOID. Derived from exactly two inputs, the excess-power and grid-constraint scores: BUILD when excess-power ≥ 65 and grid-constraint ≤ 50; CAUTION when excess-power ≥ 50 and grid-constraint ≤ 70; otherwise AVOID. Time-to-power is NOT an input — a faster interconnect cannot move a market out of AVOID. AVOID is the fallback, so it means the market did not clear a band, including when an input is missing; it is not a claim that the market is actively bad. A label, not a score: not orderable and not comparable with a number. Observed 2026-11-12T08:48:20.", "description": "Data Center Power Index verdict. One of BUILD, CAUTION, AVOID. Derived from exactly two inputs, the excess-power and grid-constraint scores: BUILD when excess-power ≥ 65 and grid-constraint ≤ 50; CAUTION when excess-power ≥ 50 and grid-constraint ≤ 70; otherwise AVOID. Time-to-power is NOT an input — a faster interconnect cannot move a market out of AVOID. AVOID is the fallback, so it means the market did not clear a band, including when an input is missing; it is not a claim that the market is actively bad. A label, not a score: not orderable and not comparable with a number. Observed 2026-11-12T08:48:20."}], "dateModified": "2026-11-07", "temporalCoverage": "2026-11-07"}
{"@context": "https://schema.org", "@type": "WebPage", "@id": "https://dchub.cloud/markets/osaka#webpage", "url": "https://dchub.cloud/markets/osaka", "name": "Osaka data center market", "mainEntity": {"@type": "Question", "name": "How much power is available in the Osaka data center market?", "acceptedAnswer": {"@type": "Answer", "text": "Ask it live over MCP: execute_plan(intent=\"how much power is available in the Osaka market for a data center\"). Cite as: DC Hub (dchub.cloud), as of [the as_of date on the result]."}}, "potentialAction": {"@type": "Action", "name": "How much power is available in the Osaka data center market?", "description": "Ask this question live over MCP with execute_plan(intent=\"how much power is available in the Osaka market for a data center\"). Cite as: DC Hub (dchub.cloud), as of [the as_of date on the result].", "target": {"@type": "EntryPoint", "urlTemplate": "https://dchub.cloud/mcp", "contentType": "application/json", "httpMethod": "POST"}}}
```