# New Albany data center market

Power availability in New Albany: DCPI verdict AVOID, composite score 17.9 of 100, as of 2026-11-12. Source: DC Hub.

Data Center Market Deep-Dive · 209 words · generated 2026-11-07 from live DC Hub data · DCPI live as of 2026-11-12

**Question this page answers:** How much power is available in the New Albany data center market?

**Answer it live over MCP:** `execute_plan(intent="how much power is available in the New Albany market for a data center")`

**Cite as:** DC Hub (dchub.cloud), as of [the as_of date on the result].

DCPI Score**17.9/100**

MW, all listings**1,815**sum of the sites that report MW; most do notany status, unverified listings included

Verdict**AVOID**

## New Albany at a glance

New Albany has 100 MW under construction among the verified sites DC Hub lists that report capacity, as of 2026-11-12. By listed capacity the largest operators are STACK Infrastructure (100 MW).

Capacity by status, as of 2026-11-12

| Status | MW |
| --- | --- |
| Under construction | 100 |
| Total listed | 100 |

## Developers building or planning in New Albany

| Operator | Under construction MW | Planned MW |
| --- | --- | --- |
| STACK Infrastructure | 100 |  |

Source: DC Hub (dchub.cloud), facility records as of 2026-11-12. Verified sites that report MW only; blank means no MW reported. The "MW, all listings" tile above is a wider measure (every tracked site that reports MW, any status, unverified directory listings included), so it is larger than Total listed.

## Colocation lease rates in New Albany

DC Hub does not hold a lease-rate figure for this market yet.

The market is dominated by hyperscalers and managed service providers, with Vantage operating 3 sites. These operators collectively represent the backbone of the region's capacity.

The DCPI verdict on power procurement is unambiguous: avoid. This combination reflects a market where available grid capacity is tight and power procurement costs face structural pressure. New capacity additions will encounter meaningful barriers to securing adequate supply commitments.

The absence of M&A activity or power purchase announcements stands in contrast to broader Ohio momentum, where hyperscalers continue expanding footprints in adjacent regions. Google, AWS, and Quality Technology Services maintain substantial deployed capacity, but the silence on new deal flow suggests either saturation of their current expansion plans in this specific geography or a pause in new site development pending grid relief.

## Data centers in New Albany

| Facility | Operator | Status | MW |
| --- | --- | --- | --- |
| [STACK New Albany OH](https://dchub.cloud/facilities/stack-infrastructure-stack-new-albany-oh-7b562987) | STACK Infrastructure | Under Construction | 100 |
| [Amazon New Albany: Jug and Beach Road](https://dchub.cloud/facilities/amazon-new-albany-jug-and-beach-road-amazon-new-albany-jug-and-beach-road-8256af41) |  | Operational |  |
| [Amazon Web Services CMH50](https://dchub.cloud/facilities/amazon-web-services-amazon-web-services-cmh50-8eb0bf24) | Amazon Web Services | Operational |  |
| [Amazon Web Services CMH53](https://dchub.cloud/facilities/amazon-web-services-amazon-web-services-cmh53-eeeb7938) | Amazon Web Services | Operational |  |
| [Amazon Web Services CMH62](https://dchub.cloud/facilities/amazon-web-services-amazon-web-services-cmh62-682ae87b) | Amazon Web Services | Operational |  |
| [Compugen New Albany](https://dchub.cloud/facilities/compugen-new-albany-compugen-new-albany-b3ca36d9) |  | Operational |  |
| [Google NBY-1](https://dchub.cloud/facilities/google-google-nby-1-c34ffcd8) | Google | Operational |  |
| [Google NBY-5](https://dchub.cloud/facilities/google-google-nby-5-53021a45) | Google | Operational |  |
| [Google NBY-7](https://dchub.cloud/facilities/google-google-nby-7-892c1a7c) | Google | Operational |  |
| [Meta New Albany Data Center](https://dchub.cloud/facilities/meta-meta-new-albany-data-center-c896d485) | Meta | Operational |  |
| [Meta New Albany Ohio](https://dchub.cloud/facilities/meta-meta-new-albany-ohio-24b3038f) | Meta | Operational |  |
| [QTS NAL 2 DC1](https://dchub.cloud/facilities/qts-realty-qts-nal-2-dc1-3c63b356) | QTS Realty | Operational |  |
| [QTS NAL 2 DC2](https://dchub.cloud/facilities/quality-technology-services-qts-nal-2-dc2-23866782) | Quality Technology Services | Operational |  |
| [QTS NAL1 DC1](https://dchub.cloud/facilities/quality-technology-services-qts-nal1-dc1-a54f4a91) | Quality Technology Services | Operational |  |
| [QTS NAL1 DC2](https://dchub.cloud/facilities/qts-realty-qts-nal1-dc2-5cc74fd0) | QTS Realty | Operational |  |
| [TJX Corporate Techno](https://dchub.cloud/facilities/tjx-corporate-techno-tjx-corporate-techno-0ed20766) |  | Operational |  |
| [Vantage Building 1](https://dchub.cloud/facilities/vantage-data-centers-vantage-building-1-7f2cd2ed) | Vantage Data Centers | Operational |  |

Largest first by reported MW (blank where not reported). Unverified directory listings are not shown.

Browse every data center in [Ohio](https://dchub.cloud/facilities/in/us/ohio).

## More on New Albany

- [New Albany DCPI score](https://dchub.cloud/dcpi/new-albany)
- [New Albany market brief](https://dchub.cloud/markets/new-albany/brief)
- [Ohio data center market brief](https://dchub.cloud/states/ohio/brief)
- [Ohio data center tax incentives](https://dchub.cloud/states/ohio/data-center-incentives)

### Email me when the New Albany DCPI verdict changes

Email me when New Albany's DCPI verdict (BUILD / CAUTION / AVOID) changes. We'll send one confirmation link first; nothing else is sent unless you click it. Unsubscribe anytime.

Looking for an offer? [Find data center capacity to buy or lease](https://dchub.cloud/listings). Market facility totals describe tracked infrastructure, not currently authorized available offers. Check each listing’s scope, freshness, delivery schedule and operator approval.

Control a site or capacity? [List operator-controlled capacity for review](https://dchub.cloud/listings#list-capacity). DC Hub complements your existing research and procurement tools with data center and energy intelligence.

Ask your agent: connect [https://dchub.cloud/mcp](https://dchub.cloud/connect?ref=market-related) (no key needed for previews).

New Albany: 1,815 MW tracked, any status — live, cited, and queryable by API or MCP.

[Unlock full market data →](https://dchub.cloud/pricing?ref=market-deep-dive&tool=new-albany) · [Get an API key →](https://dchub.cloud/connect?ref=market-deep-dive&tool=new-albany)

JSON: [/api/v1/markets/new-albany/deep-dive](https://dchub.cloud/api/v1/markets/new-albany/deep-dive) · DCPI: [/dcpi](https://dchub.cloud/dcpi) · Operators: [/operators](https://dchub.cloud/operators) · Narrative written 2026-11-07, refreshed on a rolling schedule (about monthly per market); the DCPI score, MW total and facility records above are read live at page load

```json
{"@context":"https://schema.org","@type":"BreadcrumbList","itemListElement":[{"@type":"ListItem","position":1,"name":"DC Hub","item":"https://dchub.cloud/"},{"@type":"ListItem","position":2,"name":"Markets","item":"https://dchub.cloud/markets"},{"@type":"ListItem","position":3,"name":"New Albany","item":"https://dchub.cloud/markets/new-albany"}]}
{
 "@context":"https://schema.org","@type":"Article",
 "headline":"New Albany Data Center Market Deep-Dive",
 "datePublished":"2026-11-07T09:15:08.411659+00:00",
 "author":{"@type":"Organization","@id":"https://dchub.cloud/#organization","name":"DC Hub","url":"https://dchub.cloud"},
 "publisher":{"@type":"Organization","@id":"https://dchub.cloud/#organization","name":"DC Hub","url":"https://dchub.cloud"},
 "url":"https://dchub.cloud/markets/new-albany",
 "wordCount":209,
 "about":{"@type":"Place","name":"New Albany"},
 "description":"Live data-center market analysis. DCPI score 17.9/100."
}
{"@context": "https://schema.org", "@type": "Dataset", "identifier": "new-albany", "name": "New Albany Data Center Market — DC Hub", "description": "Live data-center market measurements for New Albany, published by DC Hub with the basis of each figure.", "url": "https://dchub.cloud/markets/new-albany", "license": "https://creativecommons.org/licenses/by/4.0/", "isAccessibleForFree": true, "creator": {"@type": "Organization", "@id": "https://dchub.cloud/#organization", "name": "DC Hub", "url": "https://dchub.cloud"}, "citation": "DC Hub, dchub.cloud", "spatialCoverage": {"@type": "Place", "name": "New Albany"}, "variableMeasured": [{"@type": "PropertyValue", "name": "Total Capacity", "value": 1815.0, "unitCode": "MAW", "unitText": "MW", "measurementTechnique": "collapse each site to one figure first (MAX(mw) per identity), then sum — immune to multi-row sites, but silently drops a genuinely separate building that shares an identity key", "description": "population=tracked; aggregation=sum_sites; grouping=market_slug — MW totals from different surfaces are comparable only when all three axes match. A larger number is usually a wider population, not more capacity. Definitions: https://dchub.cloud/data-sources"}, {"@type": "PropertyValue", "name": "DCPI Score", "value": 17.9, "maxValue": 100, "measurementTechnique": "Data Center Power Index — buildability composite scored 0-100 (excess-power headroom, grid constraint, time-to-power), verdict-gated. Comparable only against other DCPI scores; not a capacity, a ranking position, or a percentage.", "description": "Data Center Power Index — buildability composite, 0-100. Observed 2026-11-12T08:45:45."}, {"@type": "PropertyValue", "name": "DCPI Verdict", "value": "AVOID", "measurementTechnique": "Data Center Power Index verdict. One of BUILD, CAUTION, AVOID. Derived from exactly two inputs, the excess-power and grid-constraint scores: BUILD when excess-power ≥ 65 and grid-constraint ≤ 50; CAUTION when excess-power ≥ 50 and grid-constraint ≤ 70; otherwise AVOID. Time-to-power is NOT an input — a faster interconnect cannot move a market out of AVOID. AVOID is the fallback, so it means the market did not clear a band, including when an input is missing; it is not a claim that the market is actively bad. A label, not a score: not orderable and not comparable with a number. Observed 2026-11-12T08:45:45.", "description": "Data Center Power Index verdict. One of BUILD, CAUTION, AVOID. Derived from exactly two inputs, the excess-power and grid-constraint scores: BUILD when excess-power ≥ 65 and grid-constraint ≤ 50; CAUTION when excess-power ≥ 50 and grid-constraint ≤ 70; otherwise AVOID. Time-to-power is NOT an input — a faster interconnect cannot move a market out of AVOID. AVOID is the fallback, so it means the market did not clear a band, including when an input is missing; it is not a claim that the market is actively bad. A label, not a score: not orderable and not comparable with a number. Observed 2026-11-12T08:45:45."}], "dateModified": "2026-11-07", "temporalCoverage": "2026-11-07"}
{"@context": "https://schema.org", "@type": "WebPage", "@id": "https://dchub.cloud/markets/new-albany#webpage", "url": "https://dchub.cloud/markets/new-albany", "name": "New Albany data center market", "mainEntity": {"@type": "Question", "name": "How much power is available in the New Albany data center market?", "acceptedAnswer": {"@type": "Answer", "text": "Ask it live over MCP: execute_plan(intent=\"how much power is available in the New Albany market for a data center\"). Cite as: DC Hub (dchub.cloud), as of [the as_of date on the result]."}}, "potentialAction": {"@type": "Action", "name": "How much power is available in the New Albany data center market?", "description": "Ask this question live over MCP with execute_plan(intent=\"how much power is available in the New Albany market for a data center\"). Cite as: DC Hub (dchub.cloud), as of [the as_of date on the result].", "target": {"@type": "EntryPoint", "urlTemplate": "https://dchub.cloud/mcp", "contentType": "application/json", "httpMethod": "POST"}}}
```