# Kansas City data center market

Power availability in Kansas City: DCPI verdict BUILD, composite score 68.8 of 100, as of 2026-11-12. Source: DC Hub.

Data Center Market Deep-Dive · 241 words · generated 2026-11-07 from live DC Hub data · DCPI live as of 2026-11-12

**Question this page answers:** How much power is available in the Kansas City data center market?

**Answer it live over MCP:** `execute_plan(intent="how much power is available in the Kansas City market for a data center")`

**Cite as:** DC Hub (dchub.cloud), as of [the as_of date on the result].

DCPI Score**68.8/100**

MW, all listings**2,351**sum of the sites that report MW; most do notany status, unverified listings included

Verdict**BUILD**

## Kansas City at a glance

Kansas City has 699 MW operational, 175 MW under construction and 102 MW planned among the verified sites DC Hub lists that report capacity, as of 2026-11-12. By listed capacity the largest operators are Meta (425 MW), Google (302 MW) and CoreWeave (100 MW).

Capacity by status, as of 2026-11-12

| Status | MW |
| --- | --- |
| Operational | 699 |
| Under construction | 175 |
| Planned | 102 |
| Total listed | 976 |

## Developers building or planning in Kansas City

| Operator | Under construction MW | Planned MW |
| --- | --- | --- |
| Google | 100 | 2 |
| Lambda |  | 100 |
| Meta | 75 |  |

Source: DC Hub (dchub.cloud), facility records as of 2026-11-12. Verified sites that report MW only; blank means no MW reported. The "MW, all listings" tile above is a wider measure (every tracked site that reports MW, any status, unverified directory listings included), so it is larger than Total listed.

## Colocation lease rates in Kansas City

Broker lease rates (CBRE/JLL): available on paid plans. Asking base rent per kW of critical IT capacity. Electricity is normally billed separately (metered pass-through), plus cross-connects and one-time fees. Signed deals, term and size change the number. Source: DC Hub estimate. Nearest covered markets Denver and Minneapolis (CBRE North America Data Center Trends H1 2026 (250+ kW): (figure on paid plans) / (figure on paid plans)); MO industrial power ~8.6 c/kWh (EIA via DC Hub).

The market hosts a diversified operator base beyond the top three, indicating established infrastructure maturity and multi-tenant appeal. Facility count and megawatt volume place Kansas City among active regional markets, though the deployment landscape includes sites under construction, planned, and unverified listings alongside operational assets.

This combination suggests that new power can be sourced and delivered to the market, though project developers will encounter real infrastructure coordination costs. The verdict does not address demand, economics, or competitive positioning; it reflects supply-side feasibility for incremental capacity.

Deal flow activity is visible but sparse in recent tracking windows. Digital Realty has also signaled expansion intent through land acquisition tied to AI-driven data center development in the region. Community and municipal pushback on proposed projects in Independence and downtown Kansas City suggests that permitting and local approval remain friction points separate from power availability. This opposition has delayed voting on downtown proposals but does not alter underlying power economics.

Regulatory and community sentiment will shape implementation velocity more than power supply over the next 18–24 months.

## Data centers in Kansas City

| Facility | Operator | Status | MW |
| --- | --- | --- | --- |
| [Meta Kansas City Data Center](https://dchub.cloud/facilities/meta-meta-kansas-city-data-center-2404224f) | Meta | Operational | 250 |
| [Google Kansas City Data Center](https://dchub.cloud/facilities/google-google-kansas-city-data-center-058c8e65) | Google | Operational | 200 |
| [CoreWeave Independence Campus](https://dchub.cloud/facilities/coreweave-coreweave-independence-campus-0563105b) | CoreWeave | Operational | 100 |
| [Google Kansas City Building 2](https://dchub.cloud/facilities/google-google-kansas-city-building-2-d17af46b) | Google | Under Construction | 100 |
| [Lambda Kansas City](https://dchub.cloud/facilities/lambda-lambda-kansas-city-55605243) | Lambda | Planned | 100 |
| [Meta Data Center](https://dchub.cloud/facilities/meta-meta-data-center-76f9ecaf) | Meta | Operational | 100 |
| [Meta Kansas City Building 2](https://dchub.cloud/facilities/meta-meta-kansas-city-building-2-dbfd6acb) | Meta | Under Construction | 75 |
| [Netrality 1102 Grand](https://dchub.cloud/facilities/netrality-netrality-1102-grand-8752967b) | Netrality | Operational | 15 |
| [LightEdge Kansas City](https://dchub.cloud/facilities/lightedge-lightedge-kansas-city-33ff82b1) | LightEdge | Operational | 10 |
| [Netrality 900 Walnut](https://dchub.cloud/facilities/netrality-netrality-900-walnut-4b68020a) | Netrality | Operational | 10 |
| [DataBank MCI2](https://dchub.cloud/facilities/databank-databank-mci2-6b97dd98) | DataBank | Operational | 8 |
| [DataBank MCI1](https://dchub.cloud/facilities/databank-databank-mci1-5d025751) | DataBank | Operational | 6 |
| [Google Kansas City #2 (Project Mica)](https://dchub.cloud/facilities/google-google-kansas-city-2-project-mica-08a9f45a) | Google | Planned | 2 |
| [1530 SWIFT - NOCIX](https://dchub.cloud/facilities/nocix-llc-1530-swift-nocix-50ab496d) | NOCIX, LLC | Operational |  |
| [Black Rock Financial Management](https://dchub.cloud/facilities/black-rock-financial-management-black-rock-financial-management-c63b61ff) |  | Operational |  |
| [Data Center Lenexa](https://dchub.cloud/facilities/data-center-lenexa-5e1971ea) |  | Operational |  |
| [IP Pathways KC1](https://dchub.cloud/facilities/ip-pathways-llc-ip-pathways-kc1-c1cec8ea) | IP Pathways, LLC | Operational |  |
| [Iron Mountain Data Center - Kansas City (KCM-1)](https://dchub.cloud/facilities/iron-mountain-data-centers-iron-mountain-data-center-kansas-city-kcm-1-1dd19302) | Iron Mountain Data Centers | Operational |  |
| [Level(3) Kansas City](https://dchub.cloud/facilities/lumen-technologies-level3-kansas-city-a6d363c8) | Lumen Technologies | Operational |  |
| [LightEdge Kansas City Subtropolis (KCI1)](https://dchub.cloud/facilities/lightedge-solutions-lightedge-kansas-city-subtropolis-kci1-2bf8ed52) | LightEdge Solutions | Operational |  |

Largest first by reported MW (blank where not reported). Unverified directory listings are not shown.

Browse every data center in [Missouri](https://dchub.cloud/facilities/in/us/missouri).

## More on Kansas City

- [Kansas City DCPI score](https://dchub.cloud/dcpi/kansas-city)
- [Kansas City market brief](https://dchub.cloud/markets/kansas-city/brief)
- [Missouri data center market brief](https://dchub.cloud/states/missouri/brief)
- [Missouri data center tax incentives](https://dchub.cloud/states/missouri/data-center-incentives)

### Email me when the Kansas City DCPI verdict changes

Email me when Kansas City's DCPI verdict (BUILD / CAUTION / AVOID) changes. We'll send one confirmation link first; nothing else is sent unless you click it. Unsubscribe anytime.

Looking for an offer? [Find data center capacity to buy or lease](https://dchub.cloud/listings). Market facility totals describe tracked infrastructure, not currently authorized available offers. Check each listing’s scope, freshness, delivery schedule and operator approval.

Control a site or capacity? [List operator-controlled capacity for review](https://dchub.cloud/listings#list-capacity). DC Hub complements your existing research and procurement tools with data center and energy intelligence.

Ask your agent: connect [https://dchub.cloud/mcp](https://dchub.cloud/connect?ref=market-related) (no key needed for previews).

Kansas City: 2,351 MW tracked, any status — live, cited, and queryable by API or MCP.

[Unlock full market data →](https://dchub.cloud/pricing?ref=market-deep-dive&tool=kansas-city) · [Get an API key →](https://dchub.cloud/connect?ref=market-deep-dive&tool=kansas-city)

JSON: [/api/v1/markets/kansas-city/deep-dive](https://dchub.cloud/api/v1/markets/kansas-city/deep-dive) · DCPI: [/dcpi](https://dchub.cloud/dcpi) · Operators: [/operators](https://dchub.cloud/operators) · Narrative written 2026-11-07, refreshed on a rolling schedule (about monthly per market); the DCPI score, MW total and facility records above are read live at page load

```json
{"@context":"https://schema.org","@type":"BreadcrumbList","itemListElement":[{"@type":"ListItem","position":1,"name":"DC Hub","item":"https://dchub.cloud/"},{"@type":"ListItem","position":2,"name":"Markets","item":"https://dchub.cloud/markets"},{"@type":"ListItem","position":3,"name":"Kansas City","item":"https://dchub.cloud/markets/kansas-city"}]}
{
 "@context":"https://schema.org","@type":"Article",
 "headline":"Kansas City Data Center Market Deep-Dive",
 "datePublished":"2026-11-07T09:03:30.695166+00:00",
 "author":{"@type":"Organization","@id":"https://dchub.cloud/#organization","name":"DC Hub","url":"https://dchub.cloud"},
 "publisher":{"@type":"Organization","@id":"https://dchub.cloud/#organization","name":"DC Hub","url":"https://dchub.cloud"},
 "url":"https://dchub.cloud/markets/kansas-city",
 "wordCount":241,
 "about":{"@type":"Place","name":"Kansas City"},
 "description":"Live data-center market analysis. DCPI score 68.8/100."
}
{"@context": "https://schema.org", "@type": "Dataset", "identifier": "kansas-city", "name": "Kansas City Data Center Market — DC Hub", "description": "Live data-center market measurements for Kansas City, published by DC Hub with the basis of each figure.", "url": "https://dchub.cloud/markets/kansas-city", "license": "https://creativecommons.org/licenses/by/4.0/", "isAccessibleForFree": true, "creator": {"@type": "Organization", "@id": "https://dchub.cloud/#organization", "name": "DC Hub", "url": "https://dchub.cloud"}, "citation": "DC Hub, dchub.cloud", "spatialCoverage": {"@type": "Place", "name": "Kansas City"}, "variableMeasured": [{"@type": "PropertyValue", "name": "Total Capacity", "value": 2351.0, "unitCode": "MAW", "unitText": "MW", "measurementTechnique": "collapse each site to one figure first (MAX(mw) per identity), then sum — immune to multi-row sites, but silently drops a genuinely separate building that shares an identity key", "description": "population=tracked; aggregation=sum_sites; grouping=market_slug — MW totals from different surfaces are comparable only when all three axes match. A larger number is usually a wider population, not more capacity. Definitions: https://dchub.cloud/data-sources"}, {"@type": "PropertyValue", "name": "DCPI Score", "value": 68.8, "maxValue": 100, "measurementTechnique": "Data Center Power Index — buildability composite scored 0-100 (excess-power headroom, grid constraint, time-to-power), verdict-gated. Comparable only against other DCPI scores; not a capacity, a ranking position, or a percentage.", "description": "Data Center Power Index — buildability composite, 0-100. Observed 2026-11-12T08:45:27."}, {"@type": "PropertyValue", "name": "DCPI Verdict", "value": "BUILD", "measurementTechnique": "Data Center Power Index verdict. One of BUILD, CAUTION, AVOID. Derived from exactly two inputs, the excess-power and grid-constraint scores: BUILD when excess-power ≥ 65 and grid-constraint ≤ 50; CAUTION when excess-power ≥ 50 and grid-constraint ≤ 70; otherwise AVOID. Time-to-power is NOT an input — a faster interconnect cannot move a market out of AVOID. AVOID is the fallback, so it means the market did not clear a band, including when an input is missing; it is not a claim that the market is actively bad. A label, not a score: not orderable and not comparable with a number. Observed 2026-11-12T08:45:27.", "description": "Data Center Power Index verdict. One of BUILD, CAUTION, AVOID. Derived from exactly two inputs, the excess-power and grid-constraint scores: BUILD when excess-power ≥ 65 and grid-constraint ≤ 50; CAUTION when excess-power ≥ 50 and grid-constraint ≤ 70; otherwise AVOID. Time-to-power is NOT an input — a faster interconnect cannot move a market out of AVOID. AVOID is the fallback, so it means the market did not clear a band, including when an input is missing; it is not a claim that the market is actively bad. A label, not a score: not orderable and not comparable with a number. Observed 2026-11-12T08:45:27."}], "dateModified": "2026-11-07", "temporalCoverage": "2026-11-07"}
{"@context": "https://schema.org", "@type": "WebPage", "@id": "https://dchub.cloud/markets/kansas-city#webpage", "url": "https://dchub.cloud/markets/kansas-city", "name": "Kansas City data center market", "mainEntity": {"@type": "Question", "name": "How much power is available in the Kansas City data center market?", "acceptedAnswer": {"@type": "Answer", "text": "Ask it live over MCP: execute_plan(intent=\"how much power is available in the Kansas City market for a data center\"). Cite as: DC Hub (dchub.cloud), as of [the as_of date on the result]."}}, "potentialAction": {"@type": "Action", "name": "How much power is available in the Kansas City data center market?", "description": "Ask this question live over MCP with execute_plan(intent=\"how much power is available in the Kansas City market for a data center\"). Cite as: DC Hub (dchub.cloud), as of [the as_of date on the result].", "target": {"@type": "EntryPoint", "urlTemplate": "https://dchub.cloud/mcp", "contentType": "application/json", "httpMethod": "POST"}}}
```