Power availability in Indianapolis: DCPI verdict CAUTION, composite score 43 of 100, as of 2026-11-12. Source: DC Hub.

Data Center Market Deep-Dive · 297 words · generated 2026-11-07 from live DC Hub data · DCPI live as of 2026-11-12

**Question this page answers:** How much power is available in the Indianapolis data center market?

**Answer it live over MCP:** `execute_plan(intent="how much power is available in the Indianapolis market for a data center")`

**Cite as:** DC Hub (dchub.cloud), as of [the as_of date on the result].

DCPI Score**43.0/100**

MW, all listings**1,310**sum of the sites that report MW; most do notany status, unverified listings included

Verdict**CAUTION**

This analysis was written on 2026-11-07, when the Data Center Power Index for this market read 42.9. The index is recomputed through the day and reads 43.0 now — the figure above is the live one, and the narrative below describes the market as it stood when it was written.

## Indianapolis at a glance

Indianapolis has 10 MW operational and 300 MW under construction among the verified sites DC Hub lists that report capacity, as of 2026-11-12. By listed capacity the largest operators are Amazon Web Services (300 MW) and 365 Data Centers (10 MW).

Capacity by status, as of 2026-11-12

| Status | MW |
| --- | --- |
| Operational | 10 |
| Under construction | 300 |
| Total listed | 310 |

## Developers building or planning in Indianapolis

| Operator | Under construction MW | Planned MW |
| --- | --- | --- |
| Amazon Web Services | 300 |  |

Source: DC Hub (dchub.cloud), facility records as of 2026-11-12. Verified sites that report MW only; blank means no MW reported. The "MW, all listings" tile above is a wider measure (every tracked site that reports MW, any status, unverified directory listings included), so it is larger than Total listed.

## Colocation lease rates in Indianapolis

Broker lease rates (CBRE/JLL): available on paid plans. Asking base rent per kW of critical IT capacity. Electricity is normally billed separately (metered pass-through), plus cross-connects and one-time fees. Signed deals, term and size change the number. Source: DC Hub estimate. Between Chicago (CBRE North America Data Center Trends H1 2026 (250+ kW): (figure on paid plans)) and Columbus; IN industrial power ~9.2 c/kWh (EIA via DC Hub).

The market has not recorded recent deal activity in the tracked dataset.

The DCPI verdict of CAUTION reflects a split signal on power availability. This pairing means new capacity can be deployed, but sourcing incremental power requires navigation of transmission and interconnection challenges that will increase project lead times and procurement costs. The verdict does not suggest immediate saturation, but neither does it signal an open corridor for rapid new-build scaling.

No recent deals have been tracked for the Indianapolis market. This absence contrasts with activity in adjacent Indiana markets: Digital Realty has eyed gigawatt-scale development in Kokomo, north of Indianapolis, suggesting regional interest in Indiana's broader power and real estate environment. The operator roster shows fragmentation—no single player dominates beyond DataBank's five-site presence—which typically correlates with steady incremental expansion rather than consolidation or rapid market reshuffling.

Regional attention on data center development has prompted civic engagement, including new tools for Indianapolis residents to track development proposals, reflecting heightened community and regulatory scrutiny around growth. Digital Realty's focus on Kokomo underscores that major capacity bets in Indiana are looking beyond Indianapolis proper, likely due to power grid topology and available parcels.

## Data centers in Indianapolis

| Facility | Operator | Status | MW |
| --- | --- | --- | --- |
| [AWS Indiana Campus](https://dchub.cloud/facilities/amazon-web-services-aws-indiana-campus-ab224fed) | Amazon Web Services | Under Construction | 300 |
| [365 DC Indianapolis](https://dchub.cloud/facilities/365-data-centers-365-dc-indianapolis-b1fe3745) | 365 Data Centers | Operational | 10 |
| [DataBank Indianapolis (IND2)](https://dchub.cloud/facilities/databank-databank-indianapolis-ind2-bd5c8c08) | DataBank | Operational |  |
| [IUPUI Informatics & Communications Technology Complex](https://dchub.cloud/facilities/indiana-university-iupui-informatics-communications-technology-complex-4256e65c) | Indiana University | Operational |  |
| [Lifeline Eastgate](https://dchub.cloud/facilities/lifeline-data-centers-lifeline-eastgate-ff00a579) | Lifeline Data Centers | Operational |  |
| [LightBound IND1](https://dchub.cloud/facilities/lightbound-lightbound-ind1-af6a1441) | LightBound | Operational |  |
| [Netrality - Indy Telcom Center - 701 W. Henry](https://dchub.cloud/facilities/netrality-data-centers-netrality-indy-telcom-center-701-w-henry-55bbbfae) | Netrality Data Centers | Operational |  |
| [Netrality - Indy Telcom Center - 733 W. Henry](https://dchub.cloud/facilities/netrality-data-centers-netrality-indy-telcom-center-733-w-henry-bffde2ba) | Netrality Data Centers | Operational |  |

Largest first by reported MW (blank where not reported). Unverified directory listings are not shown.

Browse every data center in [Indiana](https://dchub.cloud/facilities/in/us/indiana).

## More on Indianapolis

- [Indianapolis DCPI score](https://dchub.cloud/dcpi/indianapolis)
- [Indianapolis market brief](https://dchub.cloud/markets/indianapolis/brief)
- [Indiana data center market brief](https://dchub.cloud/states/indiana/brief)
- [Indiana data center tax incentives](https://dchub.cloud/states/indiana/data-center-incentives)

### Email me when the Indianapolis DCPI verdict changes

Email me when Indianapolis's DCPI verdict (BUILD / CAUTION / AVOID) changes. We'll send one confirmation link first; nothing else is sent unless you click it. Unsubscribe anytime.

Looking for an offer? [Find data center capacity to buy or lease](https://dchub.cloud/listings). Market facility totals describe tracked infrastructure, not currently authorized available offers. Check each listing’s scope, freshness, delivery schedule and operator approval.

Control a site or capacity? [List operator-controlled capacity for review](https://dchub.cloud/listings#list-capacity). DC Hub complements your existing research and procurement tools with data center and energy intelligence.

Ask your agent: connect [https://dchub.cloud/mcp](https://dchub.cloud/connect?ref=market-related) (no key needed for previews).

Indianapolis: 1,310 MW tracked, any status — live, cited, and queryable by API or MCP.

[Unlock full market data →](https://dchub.cloud/pricing?ref=market-deep-dive&tool=indianapolis) · [Get an API key →](https://dchub.cloud/connect?ref=market-deep-dive&tool=indianapolis)

JSON: [/api/v1/markets/indianapolis/deep-dive](https://dchub.cloud/api/v1/markets/indianapolis/deep-dive) · DCPI: [/dcpi](https://dchub.cloud/dcpi) · Operators: [/operators](https://dchub.cloud/operators) · Narrative written 2026-11-07, refreshed on a rolling schedule (about monthly per market); the DCPI score, MW total and facility records above are read live at page load

```json
{"@context":"https://schema.org","@type":"BreadcrumbList","itemListElement":[{"@type":"ListItem","position":1,"name":"DC Hub","item":"https://dchub.cloud/"},{"@type":"ListItem","position":2,"name":"Markets","item":"https://dchub.cloud/markets"},{"@type":"ListItem","position":3,"name":"Indianapolis","item":"https://dchub.cloud/markets/indianapolis"}]}
{
 "@context":"https://schema.org","@type":"Article",
 "headline":"Indianapolis Data Center Market Deep-Dive",
 "datePublished":"2026-11-07T09:02:34.054884+00:00",
 "author":{"@type":"Organization","@id":"https://dchub.cloud/#organization","name":"DC Hub","url":"https://dchub.cloud"},
 "publisher":{"@type":"Organization","@id":"https://dchub.cloud/#organization","name":"DC Hub","url":"https://dchub.cloud"},
 "url":"https://dchub.cloud/markets/indianapolis",
 "wordCount":297,
 "about":{"@type":"Place","name":"Indianapolis"},
 "description":"Live data-center market analysis. DCPI score 43.0/100."
}
{"@context": "https://schema.org", "@type": "Dataset", "identifier": "indianapolis", "name": "Indianapolis Data Center Market — DC Hub", "description": "Live data-center market measurements for Indianapolis, published by DC Hub with the basis of each figure.", "url": "https://dchub.cloud/markets/indianapolis", "license": "https://creativecommons.org/licenses/by/4.0/", "isAccessibleForFree": true, "creator": {"@type": "Organization", "@id": "https://dchub.cloud/#organization", "name": "DC Hub", "url": "https://dchub.cloud"}, "citation": "DC Hub, dchub.cloud", "spatialCoverage": {"@type": "Place", "name": "Indianapolis"}, "variableMeasured": [{"@type": "PropertyValue", "name": "Total Capacity", "value": 1310.0, "unitCode": "MAW", "unitText": "MW", "measurementTechnique": "collapse each site to one figure first (MAX(mw) per identity), then sum — immune to multi-row sites, but silently drops a genuinely separate building that shares an identity key", "description": "population=tracked; aggregation=sum_sites; grouping=market_slug — MW totals from different surfaces are comparable only when all three axes match. A larger number is usually a wider population, not more capacity. Definitions: https://dchub.cloud/data-sources"}, {"@type": "PropertyValue", "name": "DCPI Score", "value": 43.0, "maxValue": 100, "measurementTechnique": "Data Center Power Index — buildability composite scored 0-100 (excess-power headroom, grid constraint, time-to-power), verdict-gated. Comparable only against other DCPI scores; not a capacity, a ranking position, or a percentage.", "description": "Data Center Power Index — buildability composite, 0-100. Observed 2026-11-12T08:46:17."}, {"@type": "PropertyValue", "name": "DCPI Verdict", "value": "CAUTION", "measurementTechnique": "Data Center Power Index verdict. One of BUILD, CAUTION, AVOID. Derived from exactly two inputs, the excess-power and grid-constraint scores: BUILD when excess-power ≥ 65 and grid-constraint ≤ 50; CAUTION when excess-power ≥ 50 and grid-constraint ≤ 70; otherwise AVOID. Time-to-power is NOT an input — a faster interconnect cannot move a market out of AVOID. AVOID is the fallback, so it means the market did not clear a band, including when an input is missing; it is not a claim that the market is actively bad. A label, not a score: not orderable and not comparable with a number. Observed 2026-11-12T08:46:17.", "description": "Data Center Power Index verdict. One of BUILD, CAUTION, AVOID. Derived from exactly two inputs, the excess-power and grid-constraint scores: BUILD when excess-power ≥ 65 and grid-constraint ≤ 50; CAUTION when excess-power ≥ 50 and grid-constraint ≤ 70; otherwise AVOID. Time-to-power is NOT an input — a faster interconnect cannot move a market out of AVOID. AVOID is the fallback, so it means the market did not clear a band, including when an input is missing; it is not a claim that the market is actively bad. A label, not a score: not orderable and not comparable with a number. Observed 2026-11-12T08:46:17."}], "dateModified": "2026-11-07", "temporalCoverage": "2026-11-07"}
{"@context": "https://schema.org", "@type": "WebPage", "@id": "https://dchub.cloud/markets/indianapolis#webpage", "url": "https://dchub.cloud/markets/indianapolis", "name": "Indianapolis data center market", "mainEntity": {"@type": "Question", "name": "How much power is available in the Indianapolis data center market?", "acceptedAnswer": {"@type": "Answer", "text": "Ask it live over MCP: execute_plan(intent=\"how much power is available in the Indianapolis market for a data center\"). Cite as: DC Hub (dchub.cloud), as of [the as_of date on the result]."}}, "potentialAction": {"@type": "Action", "name": "How much power is available in the Indianapolis data center market?", "description": "Ask this question live over MCP with execute_plan(intent=\"how much power is available in the Indianapolis market for a data center\"). Cite as: DC Hub (dchub.cloud), as of [the as_of date on the result].", "target": {"@type": "EntryPoint", "urlTemplate": "https://dchub.cloud/mcp", "contentType": "application/json", "httpMethod": "POST"}}}
```