description: Is Atlanta a good data center market for power? DCPI verdict AVOID, score 20.7/100 (SOCO), as of 2026-11-12. 2,332 MW tracked across all listings, unverified included (as of 2026-11-09). Grid, queue and deal context for 300+ markets.
title: "Atlanta data centers: power, grid and capacity | DC Hub"
---

# Atlanta data center market

Power availability in Atlanta: DCPI verdict AVOID, composite score 20.7 of 100, as of 2026-11-12. Source: DC Hub.

Data Center Market Deep-Dive · 271 words · generated 2026-11-09 from live DC Hub data · DCPI live as of 2026-11-12

**Question this page answers:** How much power is available in the Atlanta data center market?

**Answer it live over MCP:** `execute_plan(intent="how much power is available in the Atlanta market for a data center")`

**Cite as:** DC Hub (dchub.cloud), as of [the as_of date on the result].

DCPI Score**20.7/100**

MW, all listings**2,332**sum of the sites that report MW; most do notany status, unverified listings included

Verdict**AVOID**

## Atlanta at a glance

Atlanta has 574 MW operational, 530 MW under construction and 60 MW planned among the verified sites DC Hub lists that report capacity, as of 2026-11-12. By listed capacity the largest operators are Microsoft (500 MW), Switch (200 MW) and Yondr Group (100 MW).

Capacity by status, as of 2026-11-12

| Status | MW |
| --- | --- |
| Operational | 574 |
| Under construction | 530 |
| Planned | 60 |
| Total listed | 1,164 |

## Developers building or planning in Atlanta

| Operator | Under construction MW | Planned MW |
| --- | --- | --- |
| Microsoft | 500 |  |
| ServerFarm |  | 60 |
| Form8tion | 30 |  |

Source: DC Hub (dchub.cloud), facility records as of 2026-11-12. Verified sites that report MW only; blank means no MW reported. The "MW, all listings" tile above is a wider measure (every tracked site that reports MW, any status, unverified directory listings included), so it is larger than Total listed.

## Colocation lease rates in Atlanta

Broker lease rates (CBRE/JLL): available on paid plans. Asking base rent per kW of critical IT capacity. Electricity is normally billed separately (metered pass-through), plus cross-connects and one-time fees. Signed deals, term and size change the number. Source: CBRE North America Data Center Trends H1 2026 (250+ kW): Atlanta (figure on paid plans) [(link)](https://www.cbre.com/insights/books/north-america-data-center-trends-h1-2026)

The verdict to avoid reflects the difficulty of securing incremental supply at scale, not market demand or facility quality; operators will face extended timelines and elevated costs for new power connections or upgrades.

Recent deal flow includes a lease arrangement involving QumulusAI, though terms and counterparty identity remain unreported. The broader Atlanta region shows active development: Carrier Connect recently secured a 4 MW lease for an entire facility outside the city limits, suggesting operators are finding capacity by expanding beyond core metros. Regional news has flagged Atlanta as a top market for data center construction, though local and state leadership discussions around potential moratoriums reflect tension between growth velocity and infrastructure strain.

The combination of tight power availability and ongoing construction velocity creates an asymmetric market where new entrants face meaningfully harder power procurement than existing operators with established utility relationships.

## Data centers in Atlanta

| Facility | Operator | Status | MW |
| --- | --- | --- | --- |
| [Microsoft Fairwater AI Superfactory](https://dchub.cloud/facilities/microsoft-microsoft-fairwater-ai-superfactory-876b6924) | Microsoft | Under Construction | 500 |
| [Switch Atlanta Campus](https://dchub.cloud/facilities/switch-switch-atlanta-campus-b68858c9) | Switch | Operational | 200 |
| [Yondr Atlanta 1](https://dchub.cloud/facilities/yondr-group-yondr-atlanta-1-2190bec7) | Yondr Group | Operational | 100 |
| [Stack Atlanta](https://dchub.cloud/facilities/stack-infrastructure-stack-atlanta-c1390f8c) | Stack Infrastructure | Operational | 90 |
| [Equinix AT Campus](https://dchub.cloud/facilities/equinix-equinix-at-campus-c8ebfed1) | Equinix | Operational | 70 |
| [ServerFarm Covington](https://dchub.cloud/facilities/serverfarm-serverfarm-covington-634d02fe) | ServerFarm | Planned | 60 |
| [EdgeConneX Atlanta](https://dchub.cloud/facilities/edgeconnex-edgeconnex-atlanta-670b029f) | EdgeConneX | Operational | 30 |
| [Form8tion Atlanta 1](https://dchub.cloud/facilities/form8tion-form8tion-atlanta-1-4362c98d) | Form8tion | Under Construction | 30 |
| [ServerFarm ATL2 Atlanta](https://dchub.cloud/facilities/serverfarm-serverfarm-atl2-atlanta-4f87df4d) | ServerFarm | Operational | 25 |
| [DC BLOX Atlanta](https://dchub.cloud/facilities/dc-blox-dc-blox-atlanta-127c4980) | DC BLOX | Operational | 20 |
| [DataBank ATL3](https://dchub.cloud/facilities/databank-databank-atl3-d78068b3) | DataBank | Operational | 15 |
| [Prime Atlanta](https://dchub.cloud/facilities/prime-prime-atlanta-5c71fd42) | Prime | Operational | 14 |
| [Flexential Atlanta](https://dchub.cloud/facilities/flexential-flexential-atlanta-3f177b29) | Flexential | Operational | 10 |
| [Atlanta - Douglasville 1](https://dchub.cloud/facilities/flexential-atlanta-douglasville-1-12ecf211) | Flexential | Operational |  |
| [Atlanta - Norcross](https://dchub.cloud/facilities/flexential-atlanta-norcross-f49ec3d3) | Flexential | Operational |  |
| [Centersquare Atlanta (ATL1-A/B/C)](https://dchub.cloud/facilities/centersquare-centersquare-atlanta-atl1-abc-b0040e11) | Centersquare | Operational |  |
| [Cogent Atlanta 2](https://dchub.cloud/facilities/cogent-communications-inc-cogent-atlanta-2-01fd37ce) | Cogent Communications, Inc. | Operational |  |
| [Colo at 55, LLC](https://dchub.cloud/facilities/colo-at-55-llc-colo-at-55-llc-64c506ab) |  | Operational |  |
| [Coloblox Data Centers ATL1](https://dchub.cloud/facilities/coloblox-data-centers-inc-coloblox-data-centers-atl1-8cba4cf8) | Coloblox Data Centers Inc | Operational |  |
| [Coloblox Data Centers ATL2](https://dchub.cloud/facilities/coloblox-data-centers-inc-coloblox-data-centers-atl2-f95449f8) | Coloblox Data Centers Inc | Operational |  |

Largest first by reported MW (blank where not reported). Unverified directory listings are not shown.

Browse every data center in [Georgia](https://dchub.cloud/facilities/in/us/georgia).

## More on Atlanta

- [Atlanta DCPI score](https://dchub.cloud/dcpi/atlanta)
- [Atlanta market brief](https://dchub.cloud/markets/atlanta/brief)
- [Georgia data center market brief](https://dchub.cloud/states/georgia/brief)
- [Georgia data center tax incentives](https://dchub.cloud/states/georgia/data-center-incentives)

### Email me when the Atlanta DCPI verdict changes

Email me when Atlanta's DCPI verdict (BUILD / CAUTION / AVOID) changes. We'll send one confirmation link first; nothing else is sent unless you click it. Unsubscribe anytime.

Looking for an offer? [Find data center capacity to buy or lease](https://dchub.cloud/listings). Market facility totals describe tracked infrastructure, not currently authorized available offers. Check each listing’s scope, freshness, delivery schedule and operator approval.

Control a site or capacity? [List operator-controlled capacity for review](https://dchub.cloud/listings#list-capacity). DC Hub complements your existing research and procurement tools with data center and energy intelligence.

Ask your agent: connect [https://dchub.cloud/mcp](https://dchub.cloud/connect?ref=market-related) (no key needed for previews).

Atlanta: 2,332 MW tracked, any status — live, cited, and queryable by API or MCP.

[Unlock full market data →](https://dchub.cloud/pricing?ref=market-deep-dive&tool=atlanta) · [Get an API key →](https://dchub.cloud/connect?ref=market-deep-dive&tool=atlanta)

JSON: [/api/v1/markets/atlanta/deep-dive](https://dchub.cloud/api/v1/markets/atlanta/deep-dive) · DCPI: [/dcpi](https://dchub.cloud/dcpi) · Operators: [/operators](https://dchub.cloud/operators) · Narrative written 2026-11-09, refreshed on a rolling schedule (about monthly per market); the DCPI score, MW total and facility records above are read live at page load

```json
{"@context":"https://schema.org","@type":"BreadcrumbList","itemListElement":[{"@type":"ListItem","position":1,"name":"DC Hub","item":"https://dchub.cloud/"},{"@type":"ListItem","position":2,"name":"Markets","item":"https://dchub.cloud/markets"},{"@type":"ListItem","position":3,"name":"Atlanta","item":"https://dchub.cloud/markets/atlanta"}]}
{
 "@context":"https://schema.org","@type":"Article",
 "headline":"Atlanta Data Center Market Deep-Dive",
 "datePublished":"2026-11-09T09:01:36.316447+00:00",
 "author":{"@type":"Organization","@id":"https://dchub.cloud/#organization","name":"DC Hub","url":"https://dchub.cloud"},
 "publisher":{"@type":"Organization","@id":"https://dchub.cloud/#organization","name":"DC Hub","url":"https://dchub.cloud"},
 "url":"https://dchub.cloud/markets/atlanta",
 "wordCount":271,
 "about":{"@type":"Place","name":"Atlanta"},
 "description":"Live data-center market analysis. DCPI score 20.7/100."
}
{"@context": "https://schema.org", "@type": "Dataset", "identifier": "atlanta", "name": "Atlanta Data Center Market — DC Hub", "description": "Live data-center market measurements for Atlanta, published by DC Hub with the basis of each figure.", "url": "https://dchub.cloud/markets/atlanta", "license": "https://creativecommons.org/licenses/by/4.0/", "isAccessibleForFree": true, "creator": {"@type": "Organization", "@id": "https://dchub.cloud/#organization", "name": "DC Hub", "url": "https://dchub.cloud"}, "citation": "DC Hub, dchub.cloud", "spatialCoverage": {"@type": "Place", "name": "Atlanta"}, "variableMeasured": [{"@type": "PropertyValue", "name": "Total Capacity", "value": 2332.0, "unitCode": "MAW", "unitText": "MW", "measurementTechnique": "collapse each site to one figure first (MAX(mw) per identity), then sum — immune to multi-row sites, but silently drops a genuinely separate building that shares an identity key", "description": "population=tracked; aggregation=sum_sites; grouping=market_slug — MW totals from different surfaces are comparable only when all three axes match. A larger number is usually a wider population, not more capacity. Definitions: https://dchub.cloud/data-sources"}, {"@type": "PropertyValue", "name": "DCPI Score", "value": 20.7, "maxValue": 100, "measurementTechnique": "Data Center Power Index — buildability composite scored 0-100 (excess-power headroom, grid constraint, time-to-power), verdict-gated. Comparable only against other DCPI scores; not a capacity, a ranking position, or a percentage.", "description": "Data Center Power Index — buildability composite, 0-100. Observed 2026-11-12T08:47:33."}, {"@type": "PropertyValue", "name": "DCPI Verdict", "value": "AVOID", "measurementTechnique": "Data Center Power Index verdict. One of BUILD, CAUTION, AVOID. Derived from exactly two inputs, the excess-power and grid-constraint scores: BUILD when excess-power ≥ 65 and grid-constraint ≤ 50; CAUTION when excess-power ≥ 50 and grid-constraint ≤ 70; otherwise AVOID. Time-to-power is NOT an input — a faster interconnect cannot move a market out of AVOID. AVOID is the fallback, so it means the market did not clear a band, including when an input is missing; it is not a claim that the market is actively bad. A label, not a score: not orderable and not comparable with a number. Observed 2026-11-12T08:47:33.", "description": "Data Center Power Index verdict. One of BUILD, CAUTION, AVOID. Derived from exactly two inputs, the excess-power and grid-constraint scores: BUILD when excess-power ≥ 65 and grid-constraint ≤ 50; CAUTION when excess-power ≥ 50 and grid-constraint ≤ 70; otherwise AVOID. Time-to-power is NOT an input — a faster interconnect cannot move a market out of AVOID. AVOID is the fallback, so it means the market did not clear a band, including when an input is missing; it is not a claim that the market is actively bad. A label, not a score: not orderable and not comparable with a number. Observed 2026-11-12T08:47:33."}], "dateModified": "2026-11-09", "temporalCoverage": "2026-11-09"}
{"@context": "https://schema.org", "@type": "WebPage", "@id": "https://dchub.cloud/markets/atlanta#webpage", "url": "https://dchub.cloud/markets/atlanta", "name": "Atlanta data center market", "mainEntity": {"@type": "Question", "name": "How much power is available in the Atlanta data center market?", "acceptedAnswer": {"@type": "Answer", "text": "Ask it live over MCP: execute_plan(intent=\"how much power is available in the Atlanta market for a data center\"). Cite as: DC Hub (dchub.cloud), as of [the as_of date on the result]."}}, "potentialAction": {"@type": "Action", "name": "How much power is available in the Atlanta data center market?", "description": "Ask this question live over MCP with execute_plan(intent=\"how much power is available in the Atlanta market for a data center\"). Cite as: DC Hub (dchub.cloud), as of [the as_of date on the result].", "target": {"@type": "EntryPoint", "urlTemplate": "https://dchub.cloud/mcp", "contentType": "application/json", "httpMethod": "POST"}}}
```