DCPI Methodology

The Data Center Power Index ranks markets on two daily-refreshing scores: Excess Power (capacity available to absorb new load) and Grid Constraint (impediments to new builds). Two scores set the verdict. Modeled time to power adds 10% to the ranking.

Composite ranking (method v2.6.0)

Each market's composite score is: excess*0.60 + (100-constraint)*0.30 + (1 - min(ttp,60)/60)*100*0.10, then multiplied by the verdict quality multiplier

InputWeight
Excess Power score60%
Inverse Grid Constraint (100 − constraint)30%
Modeled time to power10%

Time to power is capped at 60 months in the formula. The verdict multiplies the composite:

VerdictMultiplier
BUILD× 1
CAUTION× 0.85
AVOID× 0.6
LOW_SIGNAL× 0.35

Verdict bands

The first row whose both conditions hold wins; anything else is AVOID.

VerdictExcess PowerGrid Constraint
BUILDexcess ≥ 65constraint ≤ 50
CAUTIONexcess ≥ 50constraint ≤ 70

Refresh: approximately 4x/day. The as_of (computed_at) on each market row is the authoritative freshness stamp, not the cron time.

Snapshot of GET /api/v1/dcpi/methodology, baked 2026-11-04. Scoring unchanged since 2026-10-24. The input weights inside the Excess Power and Grid Constraint scores are not in the keyless payload, so they are not shown here.

Loading the live method definition…

Citation

DC Hub Data Center Power Index, dchub.cloud/dcpi, accessed .

Machine-readable source of truth: GET /api/v1/dcpi/methodology — public, no key required. Every figure on this page is rendered from that response.