{"ok": true, "slug": "time-to-power-santa-clara", "url": "https://dchub.cloud/ai-answers/time-to-power-santa-clara", "json_url": "https://dchub.cloud/ai-answers/time-to-power-santa-clara.json", "question": "How long does it take to get power for a new large load in Santa Clara?", "answer": "DC Hub's model puts the time to power for a new large load in Santa Clara at about 48 months, a model estimate and not a utility date, as of Nov 24, 2026. DC Hub's Data Center Power Index rates Santa Clara CAUTION for new data-center power, as of Nov 24, 2026.", "as_of": "2026-11-24", "published": "2026-11-24", "refreshed": "2026-11-24", "rows": [{"label": "Market", "value": "Santa Clara"}, {"label": "Grid operator or balancing authority", "value": "CAISO"}, {"label": "DCPI verdict", "value": "CAUTION, composite score 44.2 of 100, as of Nov 24, 2026. Source: DC Hub Data Center Power Index (DCPI)"}, {"label": "Modelled time to power, new large load", "value": "about 48 months, a model estimate and not a utility date, as of Nov 24, 2026. Source: DC Hub Data Center Power Index (DCPI)"}, {"label": "CAISO interconnection queue headline", "value": "164.8 GW, summed from 3 source files; the oldest is dated Jul 16, 2026, so the total is no newer than that. File dates, newest first: publicqueuereport.xlsx Nov 22, 2026; cluster-16-queue-report.xlsx Oct 16, 2026; cluster-15-interconnection-requests.xlsx Jul 16, 2026. Source: CAISO queue reports: Public Queue Report (ACTIVE, Net MWs to Grid) + Cluster 15 + Cluster 16 (NET MW POI)."}, {"label": "What DC Hub does not hold", "value": "A utility's own service date for a specific site, which the serving utility sets after its studies."}], "source": "Sources, each dated in the table above: DC Hub DCPI; CAISO queue reports: Public Queue Report (ACTIVE, Net MWs to Grid) + Cluster 15 + Cluster 16 (NET MW POI). Data: DC Hub (dchub.cloud), CC BY 4.0. No OpenStreetMap-derived layer is used on this page.", "cite_as": "DC Hub (dchub.cloud), as of Nov 24, 2026", "cite_line": "Cite as: DC Hub (dchub.cloud), \"How long does it take to get power for a new large load in Santa Clara?\", https://dchub.cloud/ai-answers/time-to-power-santa-clara, as of Nov 24, 2026.", "license": "https://creativecommons.org/licenses/by/4.0/", "creator": "DC Hub", "based_on": ["https://dchub.cloud/dcpi/methodology", "https://dchub.cloud/api/v1/dcpi/verdicts", "https://www.caiso.com/generation-transmission/generation/generator-interconnection"], "data_download": "https://dchub.cloud/api/v1/dcpi/verdicts", "related": [{"url": "https://dchub.cloud/dcpi/santa-clara", "label": "Santa Clara DCPI breakdown"}, {"url": "https://dchub.cloud/markets/santa-clara", "label": "Santa Clara market page"}, {"url": "https://dchub.cloud/ai-answers/colocation-capacity-santa-clara", "label": "Colocation capacity in Santa Clara"}, {"url": "https://dchub.cloud/grid/queue/caiso", "label": "CAISO interconnection queue"}], "mcp": "Get this live in your assistant: DC Hub MCP at https://dchub.cloud/mcp. Ask it with execute_plan(intent=\"How long does it take to get power for a new large load in Santa Clara?\"). Add to ChatGPT · Claude · Cursor", "v2": true, "evidence": {"evidence_as_of": "2026-11-24", "data_basis": null, "license_layers": [{"layer": "DCPI verdict and composite", "license_id": "CC-BY-4.0", "attribution": "DC Hub Data Center Power Index (DCPI)"}, {"layer": "Modelled time to power", "license_id": "CC-BY-4.0", "attribution": "DC Hub Data Center Power Index (DCPI)"}, {"layer": "CAISO interconnection queue headline", "license_id": "CC-BY-4.0", "attribution": "CAISO queue reports: Public Queue Report (ACTIVE, Net MWs to Grid) + Cluster 15 + Cluster 16 (NET MW POI)"}], "license_id": "CC-BY-4.0", "attribution_text": "DC Hub (dchub.cloud), CC BY 4.0", "layers": [{"layer": "DCPI verdict and composite", "data_basis": "modeled", "as_of": "2026-11-24", "source": "DC Hub Data Center Power Index (DCPI)"}, {"layer": "Modelled time to power", "data_basis": "modeled", "as_of": "2026-11-24", "source": "DC Hub Data Center Power Index (DCPI)"}, {"layer": "CAISO interconnection queue headline", "data_basis": "reported", "as_of": "2026-07-16", "source": "CAISO queue reports: Public Queue Report (ACTIVE, Net MWs to Grid) + Cluster 15 + Cluster 16 (NET MW POI)", "source_files": [{"file": "cluster-15-interconnection-requests.xlsx", "file_date": "2026-07-16"}, {"file": "cluster-16-queue-report.xlsx", "file_date": "2026-10-16"}, {"file": "publicqueuereport.xlsx", "file_date": "2026-11-22"}]}], "limitations": ["Model estimate for a new large load in the market; space that is already energized can be faster.", "The ISO-level figure describes the whole grid operator, not one site."], "coverage": {"scope": "one market", "market": "santa-clara", "figures": 3, "queue_scope": "ISO-wide, not market-specific"}, "partner_credit": null}, "stale": false, "indexable": true, "route_back": []}