How long does it take to get power for a new large load in Phoenix?

DC Hub's model puts the time to power for a new large load in Phoenix at about 42 months, a model estimate and not a utility date, as of Nov 24, 2026. DC Hub's Data Center Power Index rates Phoenix CAUTION for new data-center power, as of Nov 24, 2026.

MarketPhoenix
Grid operator or balancing authorityWECC
DCPI verdictCAUTION, composite score 43.5 of 100, as of Nov 24, 2026. Source: DC Hub Data Center Power Index (DCPI)
Modelled time to power, new large loadabout 42 months, a model estimate and not a utility date, as of Nov 24, 2026. Source: DC Hub Data Center Power Index (DCPI)
Interconnection queue headlineNone. Phoenix is served by WECC, which is not one of the ISOs DC Hub reports a queue headline for.
What DC Hub does not holdA utility's own service date for a specific site, which the serving utility sets after its studies.

Sources, each dated in the table above: DC Hub DCPI. Data: DC Hub (dchub.cloud), CC BY 4.0. No OpenStreetMap-derived layer is used on this page.

Cite as: DC Hub (dchub.cloud), "How long does it take to get power for a new large load in Phoenix?", https://dchub.cloud/ai-answers/time-to-power-phoenix, as of Nov 24, 2026.

How to read this

The time to power is a modelled estimate of how long a new large load takes to connect in this market. It is not a utility date: the serving utility sets a site's date after its own studies, and a site with an existing service point can be faster or slower. The Data Center Power Index verdict describes the outlook for new power in the market. The ISO figure, where shown, describes the whole grid operator.

DCPI is a daily score of where data centers can get grid power, across 300+ markets.

Methodology and citing

The method is published at /dcpi/methodology, and each figure above carries its own date and source. Cite the as-of date: DC Hub (dchub.cloud), as of Nov 24, 2026.

Related