{"ok": true, "slug": "pay-for-grid-upgrades-to-connect-sooner", "url": "https://dchub.cloud/ai-answers/pay-for-grid-upgrades-to-connect-sooner", "json_url": "https://dchub.cloud/ai-answers/pay-for-grid-upgrades-to-connect-sooner.json", "question": "Can a data center pay to get grid power sooner?", "answer": "It can be proposed, and it has to be approved. On Nov 19, 2026, Google and Ohio Power Company (AEP Ohio) jointly filed a proposal with the Public Utilities Commission of Ohio (PUCO) under which Google would fund the full incremental cost of advanced conductors on 15.5 miles of aging transmission lines in Columbus. The parties say this would deliver 24 MW of capacity Google has already contracted for about two years early. The filing is pending: it needs approval from PUCO and the Ohio Power Siting Board; if approved, the upgrade is expected in service by late 2028. For the market around it, DC Hub's Data Center Power Index (DCPI) rates Columbus AVOID (last changed Nov 14, 2026) and New Albany AVOID (last changed Nov 1, 2026) for new data-center power, with a modelled time to power for Columbus of over 48 months (a model band, not a utility date). A funded upgrade shortens the wait where that upgrade is what holds the load back; the DCPI reading is market-wide and does not include this filing. Figures as of Nov 23, 2026.", "as_of": "2026-11-23", "published": "2026-11-23", "refreshed": "2026-11-23", "rows": [{"label": "Columbus filing", "value": "Google and Ohio Power Company (AEP Ohio) jointly filed a proposal with the Public Utilities Commission of Ohio (PUCO) under which Google would fund the full incremental cost of advanced conductors on 15.5 miles of aging transmission lines in Columbus. The parties say this would deliver 24 MW of capacity Google has already contracted for about two years early. (Nov 19, 2026)"}, {"label": "Filing status", "value": "The filing is pending: it needs approval from PUCO and the Ohio Power Siting Board; if approved, the upgrade is expected in service by late 2028."}, {"label": "Columbus DCPI verdict", "value": "AVOID, last changed Nov 14, 2026"}, {"label": "New Albany DCPI verdict", "value": "AVOID, last changed Nov 1, 2026"}, {"label": "Columbus modelled time to power", "value": "over 48 months (model band, not a utility date)"}, {"label": "PJM generation queue", "value": "373.2 GW as of Nov 23, 2026"}], "source": "Source: DC Hub (dchub.cloud), as of Nov 23, 2026. Upstream: Google and Ohio Power Company joint announcement, Nov 19, 2026; DC Hub Data Center Power Index (DCPI); PJM cycle + serial service request status (active generation requests, sum of MFO).", "cite_as": "DC Hub (dchub.cloud), as of Nov 23, 2026", "cite_line": "Cite as: DC Hub (dchub.cloud), \"Can a data center pay to get grid power sooner?\", https://dchub.cloud/ai-answers/pay-for-grid-upgrades-to-connect-sooner, as of Nov 23, 2026.", "license": "https://creativecommons.org/licenses/by/4.0/", "creator": "DC Hub", "based_on": ["https://dchub.cloud/answers/pay-for-grid-upgrades-to-connect-sooner", "https://dchub.cloud/api/v1/dcpi/verdicts", "https://www.googlecloudpresscorner.com/2026-11-19-Google-and-Ohio-Power-Company-Announce-New-Initiative-to-Unlock-New-Capacity-with-Advanced-Transmission-Technology", "https://dchub.cloud/api/v1/interconnection-queue/snapshot"], "data_download": "https://dchub.cloud/api/v1/dcpi/verdicts", "related": [{"url": "https://dchub.cloud/answers/pay-for-grid-upgrades-to-connect-sooner", "label": "Paying for grid upgrades to connect sooner: the full dated page"}, {"url": "https://dchub.cloud/dcpi/columbus", "label": "Columbus DCPI breakdown"}, {"url": "https://dchub.cloud/markets/columbus", "label": "Columbus market page"}, {"url": "https://dchub.cloud/ai-answers/time-to-power-columbus", "label": "How long does it take to get power for a new large load in Columbus?"}, {"url": "https://dchub.cloud/answers/senate-permitting-bill-data-center-grid-connections", "label": "What does the Senate permitting bill mean for data center grid connections?"}], "mcp": "Get this live in your assistant: DC Hub MCP at https://dchub.cloud/mcp. Ask it with execute_plan(intent=\"Can a data center pay to get grid power sooner?\"). Add to ChatGPT · Claude · Cursor"}