{"ok": true, "slug": "ercot-approved-to-energize", "url": "https://dchub.cloud/ai-answers/ercot-approved-to-energize", "json_url": "https://dchub.cloud/ai-answers/ercot-approved-to-energize.json", "question": "How much large load has ERCOT approved to energize?", "answer": "ERCOT reports 9,456 MW of large loads approved to energize, as of Sep 16, 2026. Energizing new data-center and crypto loads of 75 MW or more is paused until Batch Zero eligibility verification is complete.", "as_of": "2026-09-16", "published": "2026-09-16", "refreshed": "2026-11-24", "rows": [{"label": "Approved to energize", "value": "9,456 MW"}, {"label": "As of", "value": "Sep 16, 2026"}, {"label": "Verification report due", "value": "Dec 10, 2026"}], "source": "Source: ERCOT Monthly Operational Overview, August 2026, published Sep 16, 2026. DC Hub refreshed Nov 24, 2026. Data: DC Hub (dchub.cloud), CC BY 4.0.", "cite_as": "DC Hub (dchub.cloud), as of Sep 16, 2026", "cite_line": "Cite as: DC Hub (dchub.cloud), \"How much large load has ERCOT approved to energize?\", https://dchub.cloud/ai-answers/ercot-approved-to-energize, as of Sep 16, 2026.", "license": "https://creativecommons.org/licenses/by/4.0/", "creator": "DC Hub", "based_on": ["https://www.ercot.com/files/docs/2026/08/20/Batch-Zero-Verification-and-Audit-PUCT-Presentation.pdf"], "data_download": "https://dchub.cloud/api/v1/interconnection-queue/by-iso?iso=ERCOT", "related": [{"url": "https://dchub.cloud/grid/ercot", "label": "ERCOT grid"}, {"url": "https://dchub.cloud/ai-answers/ercot-batch-zero-status", "label": "ERCOT Batch Zero"}], "mcp": "Get this live in your assistant: DC Hub MCP at https://dchub.cloud/mcp. Ask it with execute_plan(intent=\"How much large load has ERCOT approved to energize?\"). Add to ChatGPT · Claude · Cursor"}