{"ok": true, "slug": "alberta-ontario-grid-queue-data-center-demand", "url": "https://dchub.cloud/ai-answers/alberta-ontario-grid-queue-data-center-demand", "json_url": "https://dchub.cloud/ai-answers/alberta-ontario-grid-queue-data-center-demand.json", "question": "How much data center demand is in Alberta's and Ontario's grid connection queues?", "answer": "DC Hub does not publish a figure for data centers alone in Alberta's or Ontario's grid connection queues: it tracks every demand (load) project in each queue, data centers included. AESO's queue (Alberta) holds 21.6 GW of demand projects out of 27.6 GW (78%), as of Nov 17, 2026 (feed read date). IESO's queue (Ontario) holds 12.5 GW of demand projects out of 19.1 GW (65.8%), as of Nov 17, 2026 (feed read date). These queues list generation and demand together, so they are not comparable with US generation interconnection queues and are never added to them.", "as_of": "2026-11-17", "published": "2026-11-17", "refreshed": "2026-11-17", "rows": [{"label": "AESO (Alberta) demand projects in queue", "value": "21.6 GW of 27.6 GW (78%, generation and demand mixed), as of Nov 17, 2026 (feed read date)"}, {"label": "IESO (Ontario) demand projects in queue", "value": "12.5 GW of 19.1 GW (65.8%, generation and demand mixed), as of Nov 17, 2026 (feed read date)"}, {"label": "NESO (Great Britain) demand projects in queue", "value": "53.0 GW of 592.1 GW (8.9%, generation and demand mixed), as of Nov 17, 2026 (feed read date)"}], "source": "Source: DC Hub (dchub.cloud), as of Nov 17, 2026. Upstream: Alberta AESO Connection Project List (active; November-2026-Project-List.xlsx); Ontario IESO CAA connection queue (active, summer MW); UK NESO TEC Register (active connections queue, per-project MW).", "cite_as": "DC Hub (dchub.cloud), as of Nov 17, 2026", "cite_line": "Cite as: DC Hub (dchub.cloud), \"How much data center demand is in Alberta's and Ontario's grid connection queues?\", https://dchub.cloud/ai-answers/alberta-ontario-grid-queue-data-center-demand, as of Nov 17, 2026.", "license": "https://creativecommons.org/licenses/by/4.0/", "creator": "DC Hub", "based_on": ["https://dchub.cloud/answers/alberta-ontario-grid-queue-data-center-demand", "https://dchub.cloud/api/v1/interconnection-queue/snapshot", "https://dchub.cloud/interconnection-queues", "https://www.aeso.ca/grid/connecting-to-the-grid/connection-project-reporting/", "https://www.ieso.ca/en/Get-Involved/Connection-Assessments/Connection-Application-Status", "https://www.neso.energy/data-portal/transmission-entry-capacity-tec-register"], "data_download": "https://dchub.cloud/api/v1/interconnection-queue/snapshot", "related": [{"url": "https://dchub.cloud/answers/alberta-ontario-grid-queue-data-center-demand", "label": "Alberta and Ontario grid queue demand: the full dated page"}, {"url": "https://dchub.cloud/interconnection-queues", "label": "All interconnection queues (dchub.cloud/interconnection-queues)"}, {"url": "https://dchub.cloud/answers/us-interconnection-queues-by-grid", "label": "US generation interconnection queues by grid operator"}], "mcp": "Get this live in your assistant: DC Hub MCP at https://dchub.cloud/mcp. Ask it with execute_plan(intent=\"How much data center demand is in Alberta's and Ontario's grid connection queues?\"). Add to ChatGPT · Claude · Cursor"}